Habersham Development Authority reports new construction and a permitting delay at Airport Business Park

The authority continues selling and building out Phase II of the county's business park, with one building under construction and another held up by a city permitting change.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

June 11, 2026: Airport Business Park new signage for tenants

What happens next

No next step has been documented.

At a glance

What this means now

Where it stands

This spring and summer, the authority responded to a state request for information on a potential manufacturing project with details on available Phase II sites, and survey flags and construction equipment were spotted on site. In June 2026 the authority reported construction moving forward on a 10,000-square-foot building on pad 6(B), aided by an estoppel letter to help secure financing, while pad 7's permitting has been delayed by communication issues with the City of Baldwin's new permitting company. The authority also toured the park with a prospective developer among three active prospects, and tenants have asked for new signage to display their information.

The story

In early 2025 the Habersham County Development Authority worked to sell a Development Authority-owned site on Pyratich Drive in Baldwin, first voting 6-0 to amend the sale contract and then voting 6-0 to counteroffer on the property at 5.007 acres for $45,000 per acre, even as officials said activity at existing park buildings, particularly the Higgins building, was slow.

SourcesMeeting4814_Approved Minutes - January 9- 2025 Regular Meeting.pdfMeeting4880_Approved Minutes - January 22- 2025 Special Called Meeting.pdf

By February and March 2025 the authority reported two solid prospects for Phase II, with one under contract and nearing close, though a prospect called Project Hill withdrew from its contract. The Pyratich sale closed, bringing the authority proceeds of $214,049.25, while a dispute continued over Wilson Hutchinson's buyback of lots 5 and 7.

SourcesMeeting4816_Approved Minutes - February 13- 2025 Regular Meeting.pdfMeeting4815_Approved Minutes - March 13- 2025 Regular Meeting.pdf

Construction got underway on the Clearview building on the Pyratich site that spring, and Wilson-Hutchinson submitted plans and permits for a 15,000-square-foot building on pad 7. In June 2025 the authority voted 7-0 to approve updated Phase II covenants, which include an association/dues requirement and a $500-per-month penalty for construction delays, after reviewing proposed layout renderings for the phase.

SourcesMeeting4817_Approved Minutes - April 17- 2025 Regular Meeting.pdfMeeting4819_20250818112922254.pdf

Through the fall of 2025 and into early 2026, the authority pursued interest from SteelCell in an available Phase II lot while continuing to chase unpaid common-services bills from tenant GTS Customs. Officials said 15 acres remained to sell in Phase II, and by January 2026 Clear View Enterprises was finishing construction on its new building; the authority later toured that site to discuss the company's operations.

SourcesMeeting4822_Approved Minutes - October 20- 2025 Regular Meeting.pdfMeeting4824_20260109095530945.pdfMeeting5247_Minutes Draft - January 8- 2026 Regular Meeting.pdfMeeting5248_Approved Minutes - February 12- 2026 Regular Meeting.pdf

This spring and summer, the authority responded to a state request for information on a potential manufacturing project with details on available Phase II sites, and survey flags and construction equipment were spotted on site. In June 2026 the authority reported construction moving forward on a 10,000-square-foot building on pad 6(B), aided by an estoppel letter to help secure financing, while pad 7's permitting has been delayed by communication issues with the City of Baldwin's new permitting company. The authority also toured the park with a prospective developer among three active prospects, and tenants have asked for new signage to display their information.

SourcesMeeting5250_Approved Minutes - April 9- 2026 Regular Meeting.pdfMeeting5251_20260619111141165 -1-.pdfMeeting5252_20260717101949886.pdf

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Discussed
discussed

Phase I/II Airport Business Park lot discussion with SteelCell

Rope Roberts and Bryan Ferguson ate trying to arrange a meeting with SteelCell regarding an available lot in Phase H

Appeared on agenda
proposed

Phase II Business Park update

Phase II Business Park Update

Discussed
discussed

GTS Customs unpaid business park common services bills / possible letter to owner

G'S Customs has not paid any of the bills associated with the business park common setvices and owe a balance of $915.73

Appeared on agenda
proposed

Airport Business Park update, including GTS Customs letter

Airport Business Park Update o GTS Customs letter

Appeared on agenda
proposed

Phase II Business Park update

Phase II Business Park Update

Appeared on agenda
proposed

Airport Business Park update

Airport Business Park Update

Discussed
discussed

Administrative update on tenant accounts, including GTS Customs nonpayment

GTS Customs has not paid any of their invoices.

Appeared on agenda
proposed

Airport Business Park Update

1. Airport Business Park Update

Appeared on agenda
proposed

Phase II Business Park Update

2. Phase II Business Park Update

Approved
confirmed

Updated business park covenants for Phase II (association/dues requirement, $500/month construction-delay penalty)

voted 7-0 to approve the updated business park covenants for Phase II.

Appeared on agenda
proposed

Airport Business Park development update

Airport Business Park Update

Appeared on agenda
proposed

Phase II Business Park development update

Phase II Business Park Update

Discussed
discussed

Phase II Business Park layout renderings

Bryan Ferguson brought two renderings for a proposed layout for Phase II.

Appeared on agenda
proposed

Updated business park covenants for Phase II

Consider/Discuss updated business park covenants for Phase II

Discussed
discussed

Business park billing worksheet / tenant balance due

the business park billing worksheet dated 3/12/25 which shows a balance due from tenants of $2,817.04.

Discussed
discussed

Phase II Business Park update: Clearview building construction on Pyratich site

construction materials have been ordered for the Clearview building on the Pyratich site, and they will be breaking ground soon.

Appeared on agenda
proposed

Airport Business Park Update

Airport Business Park Update

Discussed
discussed

Airport Business Park update: Wilson-Hutchinson development on lots 5 and 7

Wilson-Hutchinson have submitted plans and permits to build a 15,000 square foot building on pad 7, which is across from the Higgins building.

Appeared on agenda
proposed

Updated business park covenants for Phase II

Consider/Discuss updated business park covenants for Phase II

Appeared on agenda
proposed

Phase II Business Park Update

Phase II Business Park Update

Showing 21–40 of 53 recorded steps.

Find a step on another page

These links also preserve bookmarks to earlier timeline steps.

Research the record

Search the underlying agendas, minutes, and documents.

Search supporting records