Habersham Development Authority reports steady building and land sales activity at Airport Business Park's Phase II

The county's development authority has spent nearly two years selling and amending contracts for lots, approving new park covenants, and now contracting for a Phase II master plan as several buildings go up and fill with tenants.

By NEGA Brief NewsroomLast checked November 15, 2026
Latest

October 8, 2026: Preliminary engineering estimate for Phase II

What happens next

The Development Authority's Oct. 8, 2026 agenda lists consideration/approval of a preliminary engineering estimate for Phase II.

At a glance

What this means now

Where it stands

Through mid-to-late 2026, construction moved forward on pad 6(B)'s 10,000-square-foot building, aided by an estoppel letter for financing, and on pad 7, where permitting was delayed by the City of Baldwin's new permitting company before being submitted and heavy dirt-moving began. The authority reported three prospects touring Airport Business Park and Phase II, planned new signage for tenants, and contracted with DCCM for a Phase 2 master plan covering three new industrial buildings of roughly 80,000 to 90,000 square feet each plus a roughly 20,000-square-foot building, while a separate Airport Business Park master plan was underway with a site visit planned.

The story

In January 2025 the Habersham County Development Authority described activity on existing buildings, including the Higgins building, as slow. The authority voted 6-0 to amend the sale contract for a roughly 5-acre parcel at 0 Pyratich Drive, then on Jan. 22 voted 6-0 to counteroffer on the sale at 5.007 acres for $45,000 per acre.

SourcesMeeting4814_Approved Minutes - January 9- 2025 Regular Meeting.pdfMeeting4880_Approved Minutes - January 22- 2025 Special Called Meeting.pdf

By February the authority had two prospects for Phase II, with one moving toward closing while another, described as "Project Hill," withdrew from its contract. In March the authority reported receiving $214,049.25 in proceeds from the Pyratich sale, alongside a dispute over a buyback of lots 5 and 7 involving Wilson Hutchinson.

SourcesMeeting4816_Approved Minutes - February 13- 2025 Regular Meeting.pdfMeeting4815_Approved Minutes - March 13- 2025 Regular Meeting.pdf

Construction on the Clearview building at the Pyratich site began in April, and Wilson-Hutchinson submitted plans and permits for a 15,000-square-foot building on pad 7. In June, the authority voted 7-0 to approve updated Phase II business park covenants, which included an association/dues requirement and a $500-per-month penalty for construction delays, and reviewed renderings for a proposed Phase II layout.

SourcesMeeting4817_Approved Minutes - April 17- 2025 Regular Meeting.pdfMeeting4819_20250818112922254.pdf

Through late 2025 the authority dealt with unpaid tenant accounts, including GTS Customs, while pursuing a possible SteelCell lot in Phase II and reporting 15 acres still unsold. By early 2026 Clear View Enterprises was finishing its new building and the authority toured an available Phase II site; it also responded to a state request for information on a potential manufacturing project with details on available Phase II sites.

SourcesMeeting4822_Approved Minutes - October 20- 2025 Regular Meeting.pdfMeeting4824_20260109095530945.pdfMeeting5247_Minutes Draft - January 8- 2026 Regular Meeting.pdfMeeting5248_Approved Minutes - February 12- 2026 Regular Meeting.pdf

Through mid-to-late 2026, construction moved forward on pad 6(B)'s 10,000-square-foot building, aided by an estoppel letter for financing, and on pad 7, where permitting was delayed by the City of Baldwin's new permitting company before being submitted and heavy dirt-moving began. The authority reported three prospects touring Airport Business Park and Phase II, planned new signage for tenants, and contracted with DCCM for a Phase 2 master plan covering three new industrial buildings of roughly 80,000 to 90,000 square feet each plus a roughly 20,000-square-foot building, while a separate Airport Business Park master plan was underway with a site visit planned.

SourcesMeeting5252_20260717101949886.pdfMeeting5253_Approved Minutes - July 16- 2026 Regular Meeting.pdfApproved Minutes

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Appeared on agenda
proposed

Preliminary engineering estimate for Phase II

Consider/Approve Preliminary Engineering Estimate for Phase II

Discussed
discussed

Phase 2 master plan with DCCM for three new industrial buildings

Phase 2 — The Authority contracted with DCCM to complete a master plan for Phase 2.

Discussed
discussed

Pad 7 spec building construction and permitting progress

Pad 7 — Construction materials are on site, and work is progressing. The first building is in the final

Discussed
discussed

Airport Business Park Master Plan

Airport Business Park Master Plan — Underway, with a site visit planned for next week.

Discussed
discussed

Pad 6B construction and interior permitting issues

Pad 6B — Construction continues with a prospective tenant. Issues regarding interior permitting due to code and personnel changes are actively being addressed.

Discussed
discussed

Pad 7 industrial site development (permitting and construction)

Permits were officially submitted on May 29”. Heavy dirt-moving is taking place on the site.

Discussed
discussed

Airport Business Park wayfinding signage upgrade

modern, logo-free wayfinding design that can cleanly display all the business names in the park.

Discussed
discussed

Pad 6(B) 10,000 square foot building construction and estoppel letter

Construction of a 10,000 square foot building on pad 6(B) is moving forward and Alex assisted with an estoppel letter to facilitate financing for the project.

Discussed
discussed

Pad 7 construction and permitting delays with City of Baldwin

the final permitting package has been submitted to the City of Baldwin. However, the permitting process has been delayed due to communication issues with Baldwin’s new permitting company.

Appeared on agenda
proposed

Airport Business Park signage

Airport Business Park signage

Discussed
discussed

Airport Business Park Phase II developer interest and prospects

tout of Airport Business Park and Phase II with a prospective developer who has expressed interest in moving quickly on a project. In total, there are three prospects

Discussed
discussed

Airport Business Park new signage for tenants

Several owners or tenants have reached out to Alex asking for a new sign where they can display their information.

Discussed
discussed

Airport Business Park construction and leasing update

Sutvey flags, equipment, trailers, and materials were seen on site.

Discussed
discussed

Phase II Business Park prospect update

but those will be discussed more in Executive Session.

Appeared on agenda
proposed

Phase II Business Park development update

Phase II Business Park Update

Appeared on agenda
proposed

Airport Business Park development update

Airport Business Park Update

Discussed
discussed

Airport Business Park and Phase II development update, including drone footage and Lee Arrendale property

She received a state request for information regarding a potential manufacturing project and responded accordingly with information on Phase II available sites

Appeared on agenda
proposed

Phase II Business Park Update

Phase II Business Park Update

Appeared on agenda
proposed

Airport Business Park Update

Airport Business Park Update

Appeared on agenda
proposed

Phase II Business Park update

Phase II Business Park Update

Showing 1–20 of 61 recorded steps.