This spring and summer, the authority responded to a state request for information on a potential manufacturing project with details on available Phase II sites, and survey flags and construction equipment were spotted on site. In June 2026 the authority reported construction moving forward on a 10,000-square-foot building on pad 6(B), aided by an estoppel letter to help secure financing, while pad 7's permitting has been delayed by communication issues with the City of Baldwin's new permitting company. The authority also toured the park with a prospective developer among three active prospects, and tenants have asked for new signage to display their information.
Habersham Development Authority reports new construction and a permitting delay at Airport Business Park
The authority continues selling and building out Phase II of the county's business park, with one building under construction and another held up by a city permitting change.
June 11, 2026: Airport Business Park new signage for tenants
No next step has been documented.
At a glance
What this means now
The story
In early 2025 the Habersham County Development Authority worked to sell a Development Authority-owned site on Pyratich Drive in Baldwin, first voting 6-0 to amend the sale contract and then voting 6-0 to counteroffer on the property at 5.007 acres for $45,000 per acre, even as officials said activity at existing park buildings, particularly the Higgins building, was slow.
By February and March 2025 the authority reported two solid prospects for Phase II, with one under contract and nearing close, though a prospect called Project Hill withdrew from its contract. The Pyratich sale closed, bringing the authority proceeds of $214,049.25, while a dispute continued over Wilson Hutchinson's buyback of lots 5 and 7.
Construction got underway on the Clearview building on the Pyratich site that spring, and Wilson-Hutchinson submitted plans and permits for a 15,000-square-foot building on pad 7. In June 2025 the authority voted 7-0 to approve updated Phase II covenants, which include an association/dues requirement and a $500-per-month penalty for construction delays, after reviewing proposed layout renderings for the phase.
Through the fall of 2025 and into early 2026, the authority pursued interest from SteelCell in an available Phase II lot while continuing to chase unpaid common-services bills from tenant GTS Customs. Officials said 15 acres remained to sell in Phase II, and by January 2026 Clear View Enterprises was finishing construction on its new building; the authority later toured that site to discuss the company's operations.
This spring and summer, the authority responded to a state request for information on a potential manufacturing project with details on available Phase II sites, and survey flags and construction equipment were spotted on site. In June 2026 the authority reported construction moving forward on a 10,000-square-foot building on pad 6(B), aided by an estoppel letter to help secure financing, while pad 7's permitting has been delayed by communication issues with the City of Baldwin's new permitting company. The authority also toured the park with a prospective developer among three active prospects, and tenants have asked for new signage to display their information.
What happened
How this issue got here
Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.
DiscusseddiscussedPhase I/II Airport Business Park lot discussion with SteelCell
Rope Roberts and Bryan Ferguson ate trying to arrange
a meeting with SteelCell regarding an available lot in Phase H
+
Phase I/II Airport Business Park lot discussion with SteelCell
Rope Roberts and Bryan Ferguson ate trying to arrange a meeting with SteelCell regarding an available lot in Phase H
Appeared on agendaproposedPhase II Business Park update
Phase II Business Park Update
+
Phase II Business Park update
Phase II Business Park Update
DiscusseddiscussedGTS Customs unpaid business park common services bills / possible letter to owner
G'S Customs has not paid any of the bills
associated with the business park common setvices and owe a balance of $915.73
+
GTS Customs unpaid business park common services bills / possible letter to owner
G'S Customs has not paid any of the bills associated with the business park common setvices and owe a balance of $915.73
Appeared on agendaproposedAirport Business Park update, including GTS Customs letter
Airport Business Park Update
o GTS Customs letter
+
Airport Business Park update, including GTS Customs letter
Airport Business Park Update o GTS Customs letter
Appeared on agendaproposedPhase II Business Park update
Phase II Business Park Update
+
Phase II Business Park update
Phase II Business Park Update
Appeared on agendaproposedAirport Business Park update
Airport Business Park Update
+
Airport Business Park update
Airport Business Park Update
DiscusseddiscussedAdministrative update on tenant accounts, including GTS Customs nonpayment
GTS Customs has not paid any of
their invoices.
+
Administrative update on tenant accounts, including GTS Customs nonpayment
GTS Customs has not paid any of their invoices.
Appeared on agendaproposedAirport Business Park Update
1. Airport Business Park Update
+
Airport Business Park Update
1. Airport Business Park Update
Appeared on agendaproposedPhase II Business Park Update
2. Phase II Business Park Update
+
Phase II Business Park Update
2. Phase II Business Park Update
ApprovedconfirmedUpdated business park covenants for Phase II (association/dues requirement, $500/month construction-delay penalty)
voted 7-0 to approve the updated business park
covenants for Phase II.
+
Updated business park covenants for Phase II (association/dues requirement, $500/month construction-delay penalty)
voted 7-0 to approve the updated business park covenants for Phase II.
Appeared on agendaproposedAirport Business Park development update
Airport Business Park Update
+
Airport Business Park development update
Airport Business Park Update
Appeared on agendaproposedPhase II Business Park development update
Phase II Business Park Update
+
Phase II Business Park development update
Phase II Business Park Update
DiscusseddiscussedPhase II Business Park layout renderings
Bryan Ferguson brought two renderings for a proposed
layout for Phase II.
+
Phase II Business Park layout renderings
Bryan Ferguson brought two renderings for a proposed layout for Phase II.
Appeared on agendaproposedUpdated business park covenants for Phase II
Consider/Discuss updated business park covenants for Phase II
+
Updated business park covenants for Phase II
Consider/Discuss updated business park covenants for Phase II
DiscusseddiscussedBusiness park billing worksheet / tenant balance due
the business park billing worksheet dated
3/12/25 which shows a balance due from tenants of $2,817.04.
+
Business park billing worksheet / tenant balance due
the business park billing worksheet dated 3/12/25 which shows a balance due from tenants of $2,817.04.
DiscusseddiscussedPhase II Business Park update: Clearview building construction on Pyratich site
construction materials have been ordered for the Clearview building on the Pyratich site,
and they will be breaking ground soon.
+
Phase II Business Park update: Clearview building construction on Pyratich site
construction materials have been ordered for the Clearview building on the Pyratich site, and they will be breaking ground soon.
Appeared on agendaproposedAirport Business Park Update
Airport Business Park Update
+
Airport Business Park Update
Airport Business Park Update
DiscusseddiscussedAirport Business Park update: Wilson-Hutchinson development on lots 5 and 7
Wilson-Hutchinson have submitted plans and
permits to build a 15,000 square foot building on pad 7, which is across from the
Higgins building.
+
Airport Business Park update: Wilson-Hutchinson development on lots 5 and 7
Wilson-Hutchinson have submitted plans and permits to build a 15,000 square foot building on pad 7, which is across from the Higgins building.
Appeared on agendaproposedUpdated business park covenants for Phase II
Consider/Discuss updated business park covenants for Phase II
+
Updated business park covenants for Phase II
Consider/Discuss updated business park covenants for Phase II
Appeared on agendaproposedPhase II Business Park Update
Phase II Business Park Update
+
Phase II Business Park Update
Phase II Business Park Update
Showing 21–40 of 53 recorded steps.
Find a step on another page
These links also preserve bookmarks to earlier timeline steps.
- June 11, 2026: Pad 6(B) 10,000 square foot building construction and estoppel letter
- June 11, 2026: Pad 7 construction and permitting delays with City of Baldwin
- June 11, 2026: Airport Business Park signage
- June 11, 2026: Airport Business Park Phase II developer interest and prospects
- June 11, 2026: Airport Business Park new signage for tenants
- May 14, 2026: Airport Business Park construction and leasing update
- May 14, 2026: Phase II Business Park prospect update
- May 14, 2026: Phase II Business Park development update
- May 14, 2026: Airport Business Park development update
- April 9, 2026: Airport Business Park and Phase II development update, including drone footage and Lee Arrendale property
- April 9, 2026: Phase II Business Park Update
- April 9, 2026: Airport Business Park Update
- February 12, 2026: Phase II Business Park update
- February 12, 2026: Airport Business Park update
- February 12, 2026: Phase II Business Park update: Clearview Enterprises site visit and available site for sale
- January 8, 2026: Phase II Business Park update: Clear View Enterprises building construction
- January 8, 2026: Phase II Business Park Update
- January 8, 2026: Airport Business Park Update
- November 13, 2025: Phase II Business Park update
- November 13, 2025: Phase II Airport Business Park land sales update
- April 17, 2025: Updated business park covenants for Phase II
- March 13, 2025: Streetlight billing dispute at the Habersham County Industrial Park (unpaid accounts including Windstream and GTS Customs)
- March 13, 2025: Airport Business Park/Phase II Business Park Update
- March 13, 2025: Airport Business Park/Phase II Business Park update, including Pyratich property closing proceeds and Wilson Hutchinson lots 5 and 7 buyback dispute
- February 13, 2025: Airport Business Park Phase II update - two prospects, one under contract nearing close, Project Hill prospect withdrew from contract
- February 13, 2025: Administrative update - Q4 2024 billing delay and proposal for City of Baldwin to help fund streetlights (~$90/quarter)
- February 13, 2025: Attracting new businesses to remaining lots in Phase II (industrial/business park)
- February 13, 2025: Airport Business Park/Phase II Business Park update
- January 22, 2025: Counteroffer to sell Development Authority site on O Pyratich Drive, Baldwin
- January 9, 2025: Airport Business Park / Phase II Business Park update
- January 9, 2025: Contract amendment for sale of 0 Pyratich Drive property (Airport Business Park)
- January 9, 2025: Administrative update on streetlight billing at the business park
- January 9, 2025: Airport Business Park/Phase II Business Park update