NEGAbriefLocal records made useful
IssueHabersham Countyunder consideration

Habersham Development Authority reports steady building and land sales activity at Airport Business Park's Phase II

The county's development authority has spent nearly two years selling and amending contracts for lots, approving new park covenants, and now contracting for a Phase II master plan as several buildings go up and fill with tenants.

By NEGA Brief NewsroomLast checked November 15, 2026
Latest

October 8, 2026: Preliminary engineering estimate for Phase II

What happens next

The Development Authority's Oct. 8, 2026 agenda lists consideration/approval of a preliminary engineering estimate for Phase II.

At a glance

What this means now

Where it stands

Through mid-to-late 2026, construction moved forward on pad 6(B)'s 10,000-square-foot building, aided by an estoppel letter for financing, and on pad 7, where permitting was delayed by the City of Baldwin's new permitting company before being submitted and heavy dirt-moving began. The authority reported three prospects touring Airport Business Park and Phase II, planned new signage for tenants, and contracted with DCCM for a Phase 2 master plan covering three new industrial buildings of roughly 80,000 to 90,000 square feet each plus a roughly 20,000-square-foot building, while a separate Airport Business Park master plan was underway with a site visit planned.

The story

In January 2025 the Habersham County Development Authority described activity on existing buildings, including the Higgins building, as slow. The authority voted 6-0 to amend the sale contract for a roughly 5-acre parcel at 0 Pyratich Drive, then on Jan. 22 voted 6-0 to counteroffer on the sale at 5.007 acres for $45,000 per acre.

SourcesMeeting4814_Approved Minutes - January 9- 2025 Regular Meeting.pdfMeeting4880_Approved Minutes - January 22- 2025 Special Called Meeting.pdf

By February the authority had two prospects for Phase II, with one moving toward closing while another, described as "Project Hill," withdrew from its contract. In March the authority reported receiving $214,049.25 in proceeds from the Pyratich sale, alongside a dispute over a buyback of lots 5 and 7 involving Wilson Hutchinson.

SourcesMeeting4816_Approved Minutes - February 13- 2025 Regular Meeting.pdfMeeting4815_Approved Minutes - March 13- 2025 Regular Meeting.pdf

Construction on the Clearview building at the Pyratich site began in April, and Wilson-Hutchinson submitted plans and permits for a 15,000-square-foot building on pad 7. In June, the authority voted 7-0 to approve updated Phase II business park covenants, which included an association/dues requirement and a $500-per-month penalty for construction delays, and reviewed renderings for a proposed Phase II layout.

SourcesMeeting4817_Approved Minutes - April 17- 2025 Regular Meeting.pdfMeeting4819_20250818112922254.pdf

Through late 2025 the authority dealt with unpaid tenant accounts, including GTS Customs, while pursuing a possible SteelCell lot in Phase II and reporting 15 acres still unsold. By early 2026 Clear View Enterprises was finishing its new building and the authority toured an available Phase II site; it also responded to a state request for information on a potential manufacturing project with details on available Phase II sites.

SourcesMeeting4822_Approved Minutes - October 20- 2025 Regular Meeting.pdfMeeting4824_20260109095530945.pdfMeeting5247_Minutes Draft - January 8- 2026 Regular Meeting.pdfMeeting5248_Approved Minutes - February 12- 2026 Regular Meeting.pdf

Through mid-to-late 2026, construction moved forward on pad 6(B)'s 10,000-square-foot building, aided by an estoppel letter for financing, and on pad 7, where permitting was delayed by the City of Baldwin's new permitting company before being submitted and heavy dirt-moving began. The authority reported three prospects touring Airport Business Park and Phase II, planned new signage for tenants, and contracted with DCCM for a Phase 2 master plan covering three new industrial buildings of roughly 80,000 to 90,000 square feet each plus a roughly 20,000-square-foot building, while a separate Airport Business Park master plan was underway with a site visit planned.

SourcesMeeting5252_20260717101949886.pdfMeeting5253_Approved Minutes - July 16- 2026 Regular Meeting.pdfApproved Minutes

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Appeared on agenda
proposed

Airport Business Park/Phase II Business Park update

Airport Business Park/Phase II Business Park Update

Showing 61–61 of 61 recorded steps.

Find a step on another page

These links also preserve bookmarks to earlier timeline steps.

Research the record

Search the underlying agendas, minutes, and documents.

Search supporting records