Through mid-to-late 2026, construction moved forward on pad 6(B)'s 10,000-square-foot building, aided by an estoppel letter for financing, and on pad 7, where permitting was delayed by the City of Baldwin's new permitting company before being submitted and heavy dirt-moving began. The authority reported three prospects touring Airport Business Park and Phase II, planned new signage for tenants, and contracted with DCCM for a Phase 2 master plan covering three new industrial buildings of roughly 80,000 to 90,000 square feet each plus a roughly 20,000-square-foot building, while a separate Airport Business Park master plan was underway with a site visit planned.
Habersham Development Authority reports steady building and land sales activity at Airport Business Park's Phase II
The county's development authority has spent nearly two years selling and amending contracts for lots, approving new park covenants, and now contracting for a Phase II master plan as several buildings go up and fill with tenants.
October 8, 2026: Preliminary engineering estimate for Phase II
The Development Authority's Oct. 8, 2026 agenda lists consideration/approval of a preliminary engineering estimate for Phase II.
At a glance
What this means now
The story
In January 2025 the Habersham County Development Authority described activity on existing buildings, including the Higgins building, as slow. The authority voted 6-0 to amend the sale contract for a roughly 5-acre parcel at 0 Pyratich Drive, then on Jan. 22 voted 6-0 to counteroffer on the sale at 5.007 acres for $45,000 per acre.
By February the authority had two prospects for Phase II, with one moving toward closing while another, described as "Project Hill," withdrew from its contract. In March the authority reported receiving $214,049.25 in proceeds from the Pyratich sale, alongside a dispute over a buyback of lots 5 and 7 involving Wilson Hutchinson.
Construction on the Clearview building at the Pyratich site began in April, and Wilson-Hutchinson submitted plans and permits for a 15,000-square-foot building on pad 7. In June, the authority voted 7-0 to approve updated Phase II business park covenants, which included an association/dues requirement and a $500-per-month penalty for construction delays, and reviewed renderings for a proposed Phase II layout.
Through late 2025 the authority dealt with unpaid tenant accounts, including GTS Customs, while pursuing a possible SteelCell lot in Phase II and reporting 15 acres still unsold. By early 2026 Clear View Enterprises was finishing its new building and the authority toured an available Phase II site; it also responded to a state request for information on a potential manufacturing project with details on available Phase II sites.
Through mid-to-late 2026, construction moved forward on pad 6(B)'s 10,000-square-foot building, aided by an estoppel letter for financing, and on pad 7, where permitting was delayed by the City of Baldwin's new permitting company before being submitted and heavy dirt-moving began. The authority reported three prospects touring Airport Business Park and Phase II, planned new signage for tenants, and contracted with DCCM for a Phase 2 master plan covering three new industrial buildings of roughly 80,000 to 90,000 square feet each plus a roughly 20,000-square-foot building, while a separate Airport Business Park master plan was underway with a site visit planned.
What happened
How this issue got here
Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.
DiscusseddiscussedPhase II Business Park layout renderings
Bryan Ferguson brought two renderings for a proposed
layout for Phase II.
+
Phase II Business Park layout renderings
Bryan Ferguson brought two renderings for a proposed layout for Phase II.
Appeared on agendaproposedUpdated business park covenants for Phase II
Consider/Discuss updated business park covenants for Phase II
+
Updated business park covenants for Phase II
Consider/Discuss updated business park covenants for Phase II
DiscusseddiscussedBusiness park billing worksheet / tenant balance due
the business park billing worksheet dated
3/12/25 which shows a balance due from tenants of $2,817.04.
+
Business park billing worksheet / tenant balance due
the business park billing worksheet dated 3/12/25 which shows a balance due from tenants of $2,817.04.
DiscusseddiscussedPhase II Business Park update: Clearview building construction on Pyratich site
construction materials have been ordered for the Clearview building on the Pyratich site,
and they will be breaking ground soon.
+
Phase II Business Park update: Clearview building construction on Pyratich site
construction materials have been ordered for the Clearview building on the Pyratich site, and they will be breaking ground soon.
Appeared on agendaproposedAirport Business Park Update
Airport Business Park Update
+
Airport Business Park Update
Airport Business Park Update
DiscusseddiscussedAirport Business Park update: Wilson-Hutchinson development on lots 5 and 7
Wilson-Hutchinson have submitted plans and
permits to build a 15,000 square foot building on pad 7, which is across from the
Higgins building.
+
Airport Business Park update: Wilson-Hutchinson development on lots 5 and 7
Wilson-Hutchinson have submitted plans and permits to build a 15,000 square foot building on pad 7, which is across from the Higgins building.
Appeared on agendaproposedUpdated business park covenants for Phase II
Consider/Discuss updated business park covenants for Phase II
+
Updated business park covenants for Phase II
Consider/Discuss updated business park covenants for Phase II
Appeared on agendaproposedPhase II Business Park Update
Phase II Business Park Update
+
Phase II Business Park Update
Phase II Business Park Update
DiscusseddiscussedUpdated business park covenants for Phase II
Janney will come up with a draft for
the board to review and approve at the May meeting.
+
Updated business park covenants for Phase II
Janney will come up with a draft for the board to review and approve at the May meeting.
DiscusseddiscussedStreetlight billing dispute at the Habersham County Industrial Park (unpaid accounts including Windstream and GTS Customs)
Patti said Windstream
has stopped responding to her emails, and GTS Customs has never paid.
+
Streetlight billing dispute at the Habersham County Industrial Park (unpaid accounts including Windstream and GTS Customs)
Patti said Windstream has stopped responding to her emails, and GTS Customs has never paid.
Appeared on agendaproposedAirport Business Park/Phase II Business Park Update
Airport Business Park/Phase II Business Park Update
+
Airport Business Park/Phase II Business Park Update
Airport Business Park/Phase II Business Park Update
DiscusseddiscussedAirport Business Park/Phase II Business Park update, including Pyratich property closing proceeds and Wilson Hutchinson lots 5 and 7 buyback dispute
We have received the
proceeds of $214,049.25,
+
Airport Business Park/Phase II Business Park update, including Pyratich property closing proceeds and Wilson Hutchinson lots 5 and 7 buyback dispute
We have received the proceeds of $214,049.25,
DiscusseddiscussedAirport Business Park Phase II update - two prospects, one under contract nearing close, Project Hill prospect withdrew from contract
We’ve had two solid prospects for Phase II of Airport Business park. One
is moving in a vety good direction and is under contract and will soon close
+
Airport Business Park Phase II update - two prospects, one under contract nearing close, Project Hill prospect withdrew from contract
We’ve had two solid prospects for Phase II of Airport Business park. One is moving in a vety good direction and is under contract and will soon close
DiscusseddiscussedAdministrative update - Q4 2024 billing delay and proposal for City of Baldwin to help fund streetlights (~$90/quarter)
She explained the bill would run about $90 per quarter since we are no
longer billing for landscaping
+
Administrative update - Q4 2024 billing delay and proposal for City of Baldwin to help fund streetlights (~$90/quarter)
She explained the bill would run about $90 per quarter since we are no longer billing for landscaping
Appeared on agendaproposedAttracting new businesses to remaining lots in Phase II (industrial/business park)
Attract new businesses to remaining lots in Phase II
+
Attracting new businesses to remaining lots in Phase II (industrial/business park)
Attract new businesses to remaining lots in Phase II
Appeared on agendaproposedAirport Business Park/Phase II Business Park update
Airport Business Park/Phase II Business Park Update
+
Airport Business Park/Phase II Business Park update
Airport Business Park/Phase II Business Park Update
ApprovedconfirmedCounteroffer to sell Development Authority site on O Pyratich Drive, Baldwin
Motion by Mike Franklin, seconded by Gail Thaxton, and voted unanimously (6-0) to counteroffer on the
+
Counteroffer to sell Development Authority site on O Pyratich Drive, Baldwin
Motion by Mike Franklin, seconded by Gail Thaxton, and voted unanimously (6-0) to counteroffer on the
DiscusseddiscussedAirport Business Park / Phase II Business Park update
Activity on existing buildings, particularly the Higgins building, is quite
slow.
+
Airport Business Park / Phase II Business Park update
Activity on existing buildings, particularly the Higgins building, is quite slow.
AmendedconfirmedContract amendment for sale of 0 Pyratich Drive property (Airport Business Park)
to amend the contract
for 0 Pyratich Drive in the special stipulations section with the following conditions
+
Contract amendment for sale of 0 Pyratich Drive property (Airport Business Park)
to amend the contract for 0 Pyratich Drive in the special stipulations section with the following conditions
DiscusseddiscussedAdministrative update on streetlight billing at the business park
she needs direction on
whether to continue billing the streetlights quatterly
+
Administrative update on streetlight billing at the business park
she needs direction on whether to continue billing the streetlights quatterly
Showing 41–60 of 61 recorded steps.
Find a step on another page
These links also preserve bookmarks to earlier timeline steps.
- October 8, 2026: Preliminary engineering estimate for Phase II
- September 10, 2026: Phase 2 master plan with DCCM for three new industrial buildings
- September 10, 2026: Pad 7 spec building construction and permitting progress
- September 10, 2026: Airport Business Park Master Plan
- September 10, 2026: Pad 6B construction and interior permitting issues
- July 16, 2026: Pad 7 industrial site development (permitting and construction)
- July 16, 2026: Airport Business Park wayfinding signage upgrade
- June 11, 2026: Pad 6(B) 10,000 square foot building construction and estoppel letter
- June 11, 2026: Pad 7 construction and permitting delays with City of Baldwin
- June 11, 2026: Airport Business Park signage
- June 11, 2026: Airport Business Park Phase II developer interest and prospects
- June 11, 2026: Airport Business Park new signage for tenants
- May 14, 2026: Airport Business Park construction and leasing update
- May 14, 2026: Phase II Business Park prospect update
- May 14, 2026: Phase II Business Park development update
- May 14, 2026: Airport Business Park development update
- April 9, 2026: Airport Business Park and Phase II development update, including drone footage and Lee Arrendale property
- April 9, 2026: Phase II Business Park Update
- April 9, 2026: Airport Business Park Update
- February 12, 2026: Phase II Business Park update
- February 12, 2026: Airport Business Park update
- February 12, 2026: Phase II Business Park update: Clearview Enterprises site visit and available site for sale
- January 8, 2026: Phase II Business Park update: Clear View Enterprises building construction
- January 8, 2026: Phase II Business Park Update
- January 8, 2026: Airport Business Park Update
- November 13, 2025: Phase II Business Park update
- November 13, 2025: Phase II Airport Business Park land sales update
- September 11, 2025: Phase I/II Airport Business Park lot discussion with SteelCell
- September 11, 2025: Phase II Business Park update
- September 11, 2025: GTS Customs unpaid business park common services bills / possible letter to owner
- September 11, 2025: Airport Business Park update, including GTS Customs letter
- August 14, 2025: Phase II Business Park update
- August 14, 2025: Airport Business Park update
- August 14, 2025: Administrative update on tenant accounts, including GTS Customs nonpayment
- July 10, 2025: Airport Business Park Update
- July 10, 2025: Phase II Business Park Update
- July 10, 2025: Development Authority administrative update on past-due tenant accounts (TDB Southern Enterprises, Windstream, Wade Rhodes, GI'S Customs)
- June 12, 2025: Updated business park covenants for Phase II (association/dues requirement, $500/month construction-delay penalty)
- June 12, 2025: Airport Business Park development update
- June 12, 2025: Phase II Business Park development update
- January 9, 2025: Airport Business Park/Phase II Business Park update