Habersham Development Authority reports new construction and a permitting delay at Airport Business Park

The authority continues selling and building out Phase II of the county's business park, with one building under construction and another held up by a city permitting change.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

June 11, 2026: Airport Business Park new signage for tenants

What happens next

No next step has been documented.

At a glance

What this means now

Where it stands

This spring and summer, the authority responded to a state request for information on a potential manufacturing project with details on available Phase II sites, and survey flags and construction equipment were spotted on site. In June 2026 the authority reported construction moving forward on a 10,000-square-foot building on pad 6(B), aided by an estoppel letter to help secure financing, while pad 7's permitting has been delayed by communication issues with the City of Baldwin's new permitting company. The authority also toured the park with a prospective developer among three active prospects, and tenants have asked for new signage to display their information.

The story

In early 2025 the Habersham County Development Authority worked to sell a Development Authority-owned site on Pyratich Drive in Baldwin, first voting 6-0 to amend the sale contract and then voting 6-0 to counteroffer on the property at 5.007 acres for $45,000 per acre, even as officials said activity at existing park buildings, particularly the Higgins building, was slow.

SourcesMeeting4814_Approved Minutes - January 9- 2025 Regular Meeting.pdfMeeting4880_Approved Minutes - January 22- 2025 Special Called Meeting.pdf

By February and March 2025 the authority reported two solid prospects for Phase II, with one under contract and nearing close, though a prospect called Project Hill withdrew from its contract. The Pyratich sale closed, bringing the authority proceeds of $214,049.25, while a dispute continued over Wilson Hutchinson's buyback of lots 5 and 7.

SourcesMeeting4816_Approved Minutes - February 13- 2025 Regular Meeting.pdfMeeting4815_Approved Minutes - March 13- 2025 Regular Meeting.pdf

Construction got underway on the Clearview building on the Pyratich site that spring, and Wilson-Hutchinson submitted plans and permits for a 15,000-square-foot building on pad 7. In June 2025 the authority voted 7-0 to approve updated Phase II covenants, which include an association/dues requirement and a $500-per-month penalty for construction delays, after reviewing proposed layout renderings for the phase.

SourcesMeeting4817_Approved Minutes - April 17- 2025 Regular Meeting.pdfMeeting4819_20250818112922254.pdf

Through the fall of 2025 and into early 2026, the authority pursued interest from SteelCell in an available Phase II lot while continuing to chase unpaid common-services bills from tenant GTS Customs. Officials said 15 acres remained to sell in Phase II, and by January 2026 Clear View Enterprises was finishing construction on its new building; the authority later toured that site to discuss the company's operations.

SourcesMeeting4822_Approved Minutes - October 20- 2025 Regular Meeting.pdfMeeting4824_20260109095530945.pdfMeeting5247_Minutes Draft - January 8- 2026 Regular Meeting.pdfMeeting5248_Approved Minutes - February 12- 2026 Regular Meeting.pdf

This spring and summer, the authority responded to a state request for information on a potential manufacturing project with details on available Phase II sites, and survey flags and construction equipment were spotted on site. In June 2026 the authority reported construction moving forward on a 10,000-square-foot building on pad 6(B), aided by an estoppel letter to help secure financing, while pad 7's permitting has been delayed by communication issues with the City of Baldwin's new permitting company. The authority also toured the park with a prospective developer among three active prospects, and tenants have asked for new signage to display their information.

SourcesMeeting5250_Approved Minutes - April 9- 2026 Regular Meeting.pdfMeeting5251_20260619111141165 -1-.pdfMeeting5252_20260717101949886.pdf

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Discussed
discussed

Updated business park covenants for Phase II

Janney will come up with a draft for the board to review and approve at the May meeting.

Discussed
discussed

Streetlight billing dispute at the Habersham County Industrial Park (unpaid accounts including Windstream and GTS Customs)

Patti said Windstream has stopped responding to her emails, and GTS Customs has never paid.

Appeared on agenda
proposed

Airport Business Park/Phase II Business Park Update

Airport Business Park/Phase II Business Park Update

Discussed
discussed

Airport Business Park/Phase II Business Park update, including Pyratich property closing proceeds and Wilson Hutchinson lots 5 and 7 buyback dispute

We have received the proceeds of $214,049.25,

Discussed
discussed

Airport Business Park Phase II update - two prospects, one under contract nearing close, Project Hill prospect withdrew from contract

We’ve had two solid prospects for Phase II of Airport Business park. One is moving in a vety good direction and is under contract and will soon close

Discussed
discussed

Administrative update - Q4 2024 billing delay and proposal for City of Baldwin to help fund streetlights (~$90/quarter)

She explained the bill would run about $90 per quarter since we are no longer billing for landscaping

Appeared on agenda
proposed

Attracting new businesses to remaining lots in Phase II (industrial/business park)

Attract new businesses to remaining lots in Phase II

Appeared on agenda
proposed

Airport Business Park/Phase II Business Park update

Airport Business Park/Phase II Business Park Update

Approved
confirmed

Counteroffer to sell Development Authority site on O Pyratich Drive, Baldwin

Motion by Mike Franklin, seconded by Gail Thaxton, and voted unanimously (6-0) to counteroffer on the

Discussed
discussed

Airport Business Park / Phase II Business Park update

Activity on existing buildings, particularly the Higgins building, is quite slow.

Amended
confirmed

Contract amendment for sale of 0 Pyratich Drive property (Airport Business Park)

to amend the contract for 0 Pyratich Drive in the special stipulations section with the following conditions

Discussed
discussed

Administrative update on streetlight billing at the business park

she needs direction on whether to continue billing the streetlights quatterly

Appeared on agenda
proposed

Airport Business Park/Phase II Business Park update

Airport Business Park/Phase II Business Park Update

Showing 41–53 of 53 recorded steps.

Find a step on another page

These links also preserve bookmarks to earlier timeline steps.

Research the record

Search the underlying agendas, minutes, and documents.

Search supporting records