Through mid-to-late 2026, construction moved forward on pad 6(B)'s 10,000-square-foot building, aided by an estoppel letter for financing, and on pad 7, where permitting was delayed by the City of Baldwin's new permitting company before being submitted and heavy dirt-moving began. The authority reported three prospects touring Airport Business Park and Phase II, planned new signage for tenants, and contracted with DCCM for a Phase 2 master plan covering three new industrial buildings of roughly 80,000 to 90,000 square feet each plus a roughly 20,000-square-foot building, while a separate Airport Business Park master plan was underway with a site visit planned.
Habersham Development Authority reports steady building and land sales activity at Airport Business Park's Phase II
The county's development authority has spent nearly two years selling and amending contracts for lots, approving new park covenants, and now contracting for a Phase II master plan as several buildings go up and fill with tenants.
October 8, 2026: Preliminary engineering estimate for Phase II
The Development Authority's Oct. 8, 2026 agenda lists consideration/approval of a preliminary engineering estimate for Phase II.
At a glance
What this means now
The story
In January 2025 the Habersham County Development Authority described activity on existing buildings, including the Higgins building, as slow. The authority voted 6-0 to amend the sale contract for a roughly 5-acre parcel at 0 Pyratich Drive, then on Jan. 22 voted 6-0 to counteroffer on the sale at 5.007 acres for $45,000 per acre.
By February the authority had two prospects for Phase II, with one moving toward closing while another, described as "Project Hill," withdrew from its contract. In March the authority reported receiving $214,049.25 in proceeds from the Pyratich sale, alongside a dispute over a buyback of lots 5 and 7 involving Wilson Hutchinson.
Construction on the Clearview building at the Pyratich site began in April, and Wilson-Hutchinson submitted plans and permits for a 15,000-square-foot building on pad 7. In June, the authority voted 7-0 to approve updated Phase II business park covenants, which included an association/dues requirement and a $500-per-month penalty for construction delays, and reviewed renderings for a proposed Phase II layout.
Through late 2025 the authority dealt with unpaid tenant accounts, including GTS Customs, while pursuing a possible SteelCell lot in Phase II and reporting 15 acres still unsold. By early 2026 Clear View Enterprises was finishing its new building and the authority toured an available Phase II site; it also responded to a state request for information on a potential manufacturing project with details on available Phase II sites.
Through mid-to-late 2026, construction moved forward on pad 6(B)'s 10,000-square-foot building, aided by an estoppel letter for financing, and on pad 7, where permitting was delayed by the City of Baldwin's new permitting company before being submitted and heavy dirt-moving began. The authority reported three prospects touring Airport Business Park and Phase II, planned new signage for tenants, and contracted with DCCM for a Phase 2 master plan covering three new industrial buildings of roughly 80,000 to 90,000 square feet each plus a roughly 20,000-square-foot building, while a separate Airport Business Park master plan was underway with a site visit planned.
What happened
How this issue got here
Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.
Appeared on agendaproposedPreliminary engineering estimate for Phase II
Consider/Approve Preliminary Engineering Estimate for Phase II
+
Preliminary engineering estimate for Phase II
Consider/Approve Preliminary Engineering Estimate for Phase II
DiscusseddiscussedPhase 2 master plan with DCCM for three new industrial buildings
Phase 2 — The Authority contracted with DCCM to complete a master plan for Phase 2.
+
Phase 2 master plan with DCCM for three new industrial buildings
Phase 2 — The Authority contracted with DCCM to complete a master plan for Phase 2.
DiscusseddiscussedPad 7 spec building construction and permitting progress
Pad 7 — Construction materials are on site, and work is progressing. The first building is in the final
+
Pad 7 spec building construction and permitting progress
Pad 7 — Construction materials are on site, and work is progressing. The first building is in the final
DiscusseddiscussedAirport Business Park Master Plan
Airport Business Park Master Plan — Underway, with a site visit planned for next week.
+
Airport Business Park Master Plan
Airport Business Park Master Plan — Underway, with a site visit planned for next week.
DiscusseddiscussedPad 6B construction and interior permitting issues
Pad 6B — Construction continues with a prospective tenant. Issues regarding interior permitting due
to code and personnel changes are actively being addressed.
+
Pad 6B construction and interior permitting issues
Pad 6B — Construction continues with a prospective tenant. Issues regarding interior permitting due to code and personnel changes are actively being addressed.
DiscusseddiscussedPad 7 industrial site development (permitting and construction)
Permits were officially submitted on May 29”. Heavy dirt-moving is
taking place
on the site.
+
Pad 7 industrial site development (permitting and construction)
Permits were officially submitted on May 29”. Heavy dirt-moving is taking place on the site.
DiscusseddiscussedAirport Business Park wayfinding signage upgrade
modern, logo-free wayfinding design that can cleanly display all the business names in
the park.
+
Airport Business Park wayfinding signage upgrade
modern, logo-free wayfinding design that can cleanly display all the business names in the park.
DiscusseddiscussedPad 6(B) 10,000 square foot building construction and estoppel letter
Construction of a 10,000 square foot building on pad 6(B) is moving forward and Alex
assisted with an estoppel letter to facilitate financing for the project.
+
Pad 6(B) 10,000 square foot building construction and estoppel letter
Construction of a 10,000 square foot building on pad 6(B) is moving forward and Alex assisted with an estoppel letter to facilitate financing for the project.
DiscusseddiscussedPad 7 construction and permitting delays with City of Baldwin
the final permitting package has been submitted
to the City of Baldwin. However, the permitting process has been delayed due to
communication issues with Baldwin’s new permitting company.
+
Pad 7 construction and permitting delays with City of Baldwin
the final permitting package has been submitted to the City of Baldwin. However, the permitting process has been delayed due to communication issues with Baldwin’s new permitting company.
Appeared on agendaproposedAirport Business Park signage
Airport Business Park signage
+
Airport Business Park signage
Airport Business Park signage
DiscusseddiscussedAirport Business Park Phase II developer interest and prospects
tout of Airport Business Park and Phase II with a prospective developer who has
expressed interest in moving quickly on a project. In total, there are three prospects
+
Airport Business Park Phase II developer interest and prospects
tout of Airport Business Park and Phase II with a prospective developer who has expressed interest in moving quickly on a project. In total, there are three prospects
DiscusseddiscussedAirport Business Park new signage for tenants
Several owners or tenants have reached out to Alex
asking for a new sign where they can display their information.
+
Airport Business Park new signage for tenants
Several owners or tenants have reached out to Alex asking for a new sign where they can display their information.
DiscusseddiscussedAirport Business Park construction and leasing update
Sutvey flags, equipment, trailers, and materials were seen on site.
+
Airport Business Park construction and leasing update
Sutvey flags, equipment, trailers, and materials were seen on site.
DiscusseddiscussedPhase II Business Park prospect update
but those will be discussed more in Executive Session.
+
Phase II Business Park prospect update
but those will be discussed more in Executive Session.
Appeared on agendaproposedPhase II Business Park development update
Phase II Business Park Update
+
Phase II Business Park development update
Phase II Business Park Update
Appeared on agendaproposedAirport Business Park development update
Airport Business Park Update
+
Airport Business Park development update
Airport Business Park Update
DiscusseddiscussedAirport Business Park and Phase II development update, including drone footage and Lee Arrendale property
She received a state request for information
regarding a potential manufacturing project and responded accordingly with information
on Phase II available sites
+
Airport Business Park and Phase II development update, including drone footage and Lee Arrendale property
She received a state request for information regarding a potential manufacturing project and responded accordingly with information on Phase II available sites
Appeared on agendaproposedPhase II Business Park Update
Phase II Business Park Update
+
Phase II Business Park Update
Phase II Business Park Update
Appeared on agendaproposedAirport Business Park Update
Airport Business Park Update
+
Airport Business Park Update
Airport Business Park Update
Appeared on agendaproposedPhase II Business Park update
Phase II Business Park Update
+
Phase II Business Park update
Phase II Business Park Update
Showing 1–20 of 61 recorded steps.
Find a step on another page
These links also preserve bookmarks to earlier timeline steps.
- February 12, 2026: Airport Business Park update
- February 12, 2026: Phase II Business Park update: Clearview Enterprises site visit and available site for sale
- January 8, 2026: Phase II Business Park update: Clear View Enterprises building construction
- January 8, 2026: Phase II Business Park Update
- January 8, 2026: Airport Business Park Update
- November 13, 2025: Phase II Business Park update
- November 13, 2025: Phase II Airport Business Park land sales update
- September 11, 2025: Phase I/II Airport Business Park lot discussion with SteelCell
- September 11, 2025: Phase II Business Park update
- September 11, 2025: GTS Customs unpaid business park common services bills / possible letter to owner
- September 11, 2025: Airport Business Park update, including GTS Customs letter
- August 14, 2025: Phase II Business Park update
- August 14, 2025: Airport Business Park update
- August 14, 2025: Administrative update on tenant accounts, including GTS Customs nonpayment
- July 10, 2025: Airport Business Park Update
- July 10, 2025: Phase II Business Park Update
- July 10, 2025: Development Authority administrative update on past-due tenant accounts (TDB Southern Enterprises, Windstream, Wade Rhodes, GI'S Customs)
- June 12, 2025: Updated business park covenants for Phase II (association/dues requirement, $500/month construction-delay penalty)
- June 12, 2025: Airport Business Park development update
- June 12, 2025: Phase II Business Park development update
- June 12, 2025: Phase II Business Park layout renderings
- June 12, 2025: Updated business park covenants for Phase II
- April 17, 2025: Business park billing worksheet / tenant balance due
- April 17, 2025: Phase II Business Park update: Clearview building construction on Pyratich site
- April 17, 2025: Airport Business Park Update
- April 17, 2025: Airport Business Park update: Wilson-Hutchinson development on lots 5 and 7
- April 17, 2025: Updated business park covenants for Phase II
- April 17, 2025: Phase II Business Park Update
- April 17, 2025: Updated business park covenants for Phase II
- March 13, 2025: Streetlight billing dispute at the Habersham County Industrial Park (unpaid accounts including Windstream and GTS Customs)
- March 13, 2025: Airport Business Park/Phase II Business Park Update
- March 13, 2025: Airport Business Park/Phase II Business Park update, including Pyratich property closing proceeds and Wilson Hutchinson lots 5 and 7 buyback dispute
- February 13, 2025: Airport Business Park Phase II update - two prospects, one under contract nearing close, Project Hill prospect withdrew from contract
- February 13, 2025: Administrative update - Q4 2024 billing delay and proposal for City of Baldwin to help fund streetlights (~$90/quarter)
- February 13, 2025: Attracting new businesses to remaining lots in Phase II (industrial/business park)
- February 13, 2025: Airport Business Park/Phase II Business Park update
- January 22, 2025: Counteroffer to sell Development Authority site on O Pyratich Drive, Baldwin
- January 9, 2025: Airport Business Park / Phase II Business Park update
- January 9, 2025: Contract amendment for sale of 0 Pyratich Drive property (Airport Business Park)
- January 9, 2025: Administrative update on streetlight billing at the business park
- January 9, 2025: Airport Business Park/Phase II Business Park update