The runway closed from February 16 to March 6, 2026 for installation of new LED runway, threshold and taxiway lights, a new beacon and updated signage, with work having begun February 2. A final walkthrough in May 2026 turned up minor punch-list items, and by July the commission said the contractor had officially completed the punch list and removed leftover materials. As of the August 2026 meeting, about $117,000 remained unpaid pending the project's closeout.
Habersham County completes airport runway lighting project, final payment still pending
A GDOT-funded rebuild of the airport's runway and taxiway lighting is finished after a monthlong runway closure, but the county has not yet paid out roughly $117,000 held back from the contractor.
August 11, 2026: Airport lighting project retainage payment pending closeout
No next step has been documented.
At a glance
What this means now
The story
In early 2025 the Habersham County Airport Commission said a runway and taxiway lighting project was in design, with the Georgia Department of Transportation planning to fund the runway and taxiway lighting work together.
The project went out to bid in April 2025 and closed May 6. The Airport Commission voted 5-0 on May 13 to recommend awarding the bid to R.G. Tenney, the low bidder at $1,176,600, which the commission said was under its budgeted amount. The Habersham County Board of Commissioners voted 5-0 on May 19 to award the bid and authorize the county manager to sign related documents; a GDOT contract before the board capped state reimbursement at $882,450 or 75% of the $1,176,600 construction cost, whichever is less.
By September 2025 the construction contract with RG Tenney Electrical had been executed, with a 30-day contract time that included a 15-day runway closure. In October the Airport Commission said the contractor was still waiting on materials and would not start until all materials were on site; by November the commission said phase one was slated to begin January 5, 2026.
The runway closed from February 16 to March 6, 2026 for installation of new LED runway, threshold and taxiway lights, a new beacon and updated signage, with work having begun February 2. A final walkthrough in May 2026 turned up minor punch-list items, and by July the commission said the contractor had officially completed the punch list and removed leftover materials. As of the August 2026 meeting, about $117,000 remained unpaid pending the project's closeout.
What happened
How this issue got here
Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.
Appeared on agendaproposedAirport improvement project update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport improvement project update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
Appeared on agendaproposedPresentation on airport basics by Lead Edge Design Group ("Airport 101")
Presentation – “Airport 101” – Lead Edge Design Group
+
Presentation on airport basics by Lead Edge Design Group ("Airport 101")
Presentation – “Airport 101” – Lead Edge Design Group
Appeared on agendaproposedGDOT contract for Habersham County Airport airfield lighting rehabilitation (Limited Participation)
THE
AMOUNT SHALL NOT EXCEED
$882,450.00 OR 75%, WHICHEVER IS
LESS OF THE ACTUAL CONSTRUCTION
COST OF $1,176,600.00 TO
REHABILITATE AIRFIELD LIGHTING
+
GDOT contract for Habersham County Airport airfield lighting rehabilitation (Limited Participation)
THE AMOUNT SHALL NOT EXCEED $882,450.00 OR 75%, WHICHEVER IS LESS OF THE ACTUAL CONSTRUCTION COST OF $1,176,600.00 TO REHABILITATE AIRFIELD LIGHTING
ApprovedconfirmedAward of bid for Airport Lighting Project
Award of Bid for Airport Lighting Project and to Designate the County Manager
as an Authorized Signer for Related Document
+
Award of bid for Airport Lighting Project
Award of Bid for Airport Lighting Project and to Designate the County Manager as an Authorized Signer for Related Document
Appeared on agendaproposedAward of Bid for Airport Lighting Project
Consider/Approve Award of Bid for Airport Lighting Project and to Designate the County Manager
as an Authorized Signer for Related Document
+
Award of Bid for Airport Lighting Project
Consider/Approve Award of Bid for Airport Lighting Project and to Designate the County Manager as an Authorized Signer for Related Document
Appeared on agendaproposedAirport Airfield Lighting Project - bid acceptance and construction contracts
seek approval for the acceptance of bids, execution of construction contracts and approve the total local match for the construction of the Airport Airfield Lighting Project
+
Airport Airfield Lighting Project - bid acceptance and construction contracts
seek approval for the acceptance of bids, execution of construction contracts and approve the total local match for the construction of the Airport Airfield Lighting Project
Appeared on agendaproposedBid tabulation for the Airfield Lighting Project
Review/Approve bid tabulation for the Airfield Lighting Project and recommend approval from the Board of
Commissioners
+
Bid tabulation for the Airfield Lighting Project
Review/Approve bid tabulation for the Airfield Lighting Project and recommend approval from the Board of Commissioners
ApprovedconfirmedAirfield Lighting Project bid award recommendation to R.G. Tenney
R.G. Tenney was the lowest bid at $1,176,600, which is under our budgeted amount.
+
Airfield Lighting Project bid award recommendation to R.G. Tenney
R.G. Tenney was the lowest bid at $1,176,600, which is under our budgeted amount.
DiscusseddiscussedAirport runway lighting project out for bid
The next project is the lighting project. It is out for bid right now and closes on May 6
+
Airport runway lighting project out for bid
The next project is the lighting project. It is out for bid right now and closes on May 6
Appeared on agendaproposedAirport update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
DiscusseddiscussedRunway and taxiway lighting project bid package (GDOT-funded)
GDOT is planning to fund the runway and taxiway
lighting at the same time.
+
Runway and taxiway lighting project bid package (GDOT-funded)
GDOT is planning to fund the runway and taxiway lighting at the same time.
Appeared on agendaproposedAirport project update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport project update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
Appeared on agendaproposedAirport project update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport project update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
DiscusseddiscussedAirport lighting project design phase, pending GDOT comments
The main project we have right now
is the lighting project, which is in design phase.
+
Airport lighting project design phase, pending GDOT comments
The main project we have right now is the lighting project, which is in design phase.
Appeared on agendaproposedAirport Update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport Update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
Showing 21–35 of 35 recorded steps.
Find a step on another page
These links also preserve bookmarks to earlier timeline steps.
- August 11, 2026: Airport project update from Kimley-Horn consultant Rebecca Collins
- August 11, 2026: Airport lighting project retainage payment pending closeout
- July 14, 2026: Runway overlay project completion by contractor
- July 14, 2026: Airport project update presented by Rebecca Collins of Kimley-Horn
- May 12, 2026: Airport update presentation from Lead Edge Design Group
- May 12, 2026: Runway/taxiway lighting project punch-list and final walkthrough with Lead Edge Design Group
- April 14, 2026: Airport project update from Lead Edge Design Group
- February 10, 2026: Runway lighting project and related runway closure
- January 13, 2026: Airfield lighting project and runway closure for LED lighting installation
- January 13, 2026: Airport improvement project update from Lead Edge Design Group
- November 18, 2025: Runway and taxiway LED lighting project with Lead Edge Design Group
- November 18, 2025: Airport update from Lead Edge Design Group
- October 20, 2025: Airport lighting project with Lead Edge Design Group
- October 20, 2025: Airport update from Lead Edge Design Group
- September 16, 2025: Runway Lighting Project with GDOT and contractor RG Tenney Electrical
- September 16, 2025: Airport Update from Lead Edge Design Group
- July 8, 2025: Runway rehabilitation/lighting project with Lead Edge Design Group (grant contract, contractor submittals, planned runway closure)
- July 8, 2025: Airport development update from Lead Edge Design Group
- June 30, 2025: Airport field lighting project
- June 10, 2025: Airport runway/taxiway lighting project (grant-funded, Lead Edge Design Group)