Phase 2, construction of the amphitheater, went out for bid in April 2026, and on May 5, 2026 the Commission voted 3-0 to award the construction contract to Charles Black Construction, with amounts reported as $2,779,431 and $3,473,230. By July 2026 the contractor had begun work on the amphitheater's construction.
Cornelia amphitheater contractor begins construction after bond financing and contract award
The city financed its long-running downtown amphitheater project with a bond through the Urban Redevelopment Agency and awarded the construction contract, and work is now underway on the park site.
July 7, 2026: Amphitheater construction progress update
No next step has been documented.
At a glance
What this means now
The story
In January 2025 the Cornelia City Commission approved the engineer's recommendation for the Amphitheater Park Project and voted 4-0 to award the Phase 1 bid to Higgins Construction for $1,833,489, plus a $200,000 allowance for restrooms.
The project hit a delay in February 2025 from an EPA issue. In May and July 2025 the Commission approved change orders with Higgins Construction to replace cast iron water lines on Martin Luther King Boulevard and Clarkesville Street, at amounts reported as $178,220 and $179,840.
Through the second half of 2025 the city worked on how to pay for the amphitheater itself, meeting to explore funding options and settling on a bond issued through the Urban Redevelopment Agency; the Commission voted 4-0 in September to approve a letter of intent with Raymond James for funding advisory services, with the bond process expected to take about 75 days. Parking on Clarkesville Street was installed and Grant Place and Martin Luther King were paved, and the Hospitality & Tourism Board reviewed the amphitheater design plans in August.
The Commission voted 4-0 on February 10, 2026 to approve a bond resolution authorizing an agreement with the Urban Redevelopment Agency to finance the project, with a bond issuance reported at $4,155,000, and approved the related bond paperwork authorizing the mayor to sign.
Phase 2, construction of the amphitheater, went out for bid in April 2026, and on May 5, 2026 the Commission voted 3-0 to award the construction contract to Charles Black Construction, with amounts reported as $2,779,431 and $3,473,230. By July 2026 the contractor had begun work on the amphitheater's construction.
What happened
How this issue got here
Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.
ApprovedconfirmedPark Project change order for cast iron water line replacement on Martin Luther King/Clarkesville Street
recommends a change order to the
contract with Higgins Construction in the amount of $178,220 to complete
+
Park Project change order for cast iron water line replacement on Martin Luther King/Clarkesville Street
recommends a change order to the contract with Higgins Construction in the amount of $178,220 to complete
DiscusseddiscussedDowntown amphitheater project delayed by EPA issue
The amphitheater has run into a slight problem
with EPA which will delay it slightly.
+
Downtown amphitheater project delayed by EPA issue
The amphitheater has run into a slight problem with EPA which will delay it slightly.
ApprovedconfirmedEngineer's Recommendation for the Amphitheater Park Project
Engineer’s Recommendation for the Amphitheater Park Project
Tab L Approved 4 - 0
+
Engineer's Recommendation for the Amphitheater Park Project
Engineer’s Recommendation for the Amphitheater Park Project Tab L Approved 4 - 0
Appeared on agendaproposedEngineer's Recommendation for the Amphitheater Park Project
Engineer’s Recommendation for the Amphitheater Park Project
+
Engineer's Recommendation for the Amphitheater Park Project
Engineer’s Recommendation for the Amphitheater Park Project
ApprovedconfirmedBid award to Higgins Construction for Amphitheater Park Project Phase 1
Commissioner Bagwell made a motion to
approve the bid from Higgins Construction of $1,833,489 and make an
allowance of $200,000 for the restrooms
+
Bid award to Higgins Construction for Amphitheater Park Project Phase 1
Commissioner Bagwell made a motion to approve the bid from Higgins Construction of $1,833,489 and make an allowance of $200,000 for the restrooms
Showing 21–25 of 25 recorded steps.
Find a step on another page
These links also preserve bookmarks to earlier timeline steps.
- July 7, 2026: New city park construction (lighting, restrooms, epoxy floors, fencing)
- July 7, 2026: Park project construction progress (restrooms, concrete, lighting, Clarkesville/Grant Place/MLK paving)
- July 7, 2026: Amphitheater construction funding through bond process and ARC grant
- July 7, 2026: Amphitheater construction progress update
- May 5, 2026: Recommendation for Amphitheater Contractor
- May 5, 2026: Amphitheater Project construction contract awarded to Charles Black Construction
- April 14, 2026: City park amphitheater (Phase 2) construction out for bid
- February 10, 2026: Bond Resolution authorizing agreement with Urban Redevelopment Agency to finance the Downtown Amphitheater Project
- February 10, 2026: Bond paperwork for the Amphitheater Project
- February 3, 2026: Bond paperwork for the amphitheater project
- November 4, 2025: Amphitheater design review with Carter & Sloope
- October 7, 2025: Amphitheater project bond financing exploration with Raymond James
- September 2, 2025: Bond financing for amphitheater construction through the Urban Redevelopment Agency
- September 2, 2025: Letter of Intent with Raymond James
- September 2, 2025: Letter of Intent with Raymond James for Amphitheater funding advisory services
- August 31, 2025: Bond financing for amphitheater construction through Urban Redevelopment Agency
- August 14, 2025: Amphitheater construction plans review
- July 22, 2025: Clarkesville St. water line improvements for amphitheater/MLK project
- May 6, 2025: Park Project Change Order for Water Line Replacement
- May 6, 2025: Park project change order for water line replacement