IssueCorneliaapproved

Cornelia amphitheater contractor begins construction after bond financing and contract award

The city financed its long-running downtown amphitheater project with a bond through the Urban Redevelopment Agency and awarded the construction contract, and work is now underway on the park site.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

July 7, 2026: Amphitheater construction progress update

What happens next

No next step has been documented.

At a glance

What this means now

Where it stands

Phase 2, construction of the amphitheater, went out for bid in April 2026, and on May 5, 2026 the Commission voted 3-0 to award the construction contract to Charles Black Construction, with amounts reported as $2,779,431 and $3,473,230. By July 2026 the contractor had begun work on the amphitheater's construction.

The story

In January 2025 the Cornelia City Commission approved the engineer's recommendation for the Amphitheater Park Project and voted 4-0 to award the Phase 1 bid to Higgins Construction for $1,833,489, plus a $200,000 allowance for restrooms.

SourcesCommission Agenda Summary January 2025 127.9 KBJanuary 2025 City Commission Minutes 157.4 KB

The project hit a delay in February 2025 from an EPA issue. In May and July 2025 the Commission approved change orders with Higgins Construction to replace cast iron water lines on Martin Luther King Boulevard and Clarkesville Street, at amounts reported as $178,220 and $179,840.

Sources2025-Febuary-DDA- Minutes 1 1.2 MBCommission Agenda Summary May 2025 120.2 KBMay Minutes 2025 120.2 KB2nd Quarter Mintues 2025 Meeting 109.5 KB

Through the second half of 2025 the city worked on how to pay for the amphitheater itself, meeting to explore funding options and settling on a bond issued through the Urban Redevelopment Agency; the Commission voted 4-0 in September to approve a letter of intent with Raymond James for funding advisory services, with the bond process expected to take about 75 days. Parking on Clarkesville Street was installed and Grant Place and Martin Luther King were paved, and the Hospitality & Tourism Board reviewed the amphitheater design plans in August.

SourcesCity Manager's Monthly Report for August 2025 4.6 MBSeptember 2025 City Commission Minutes 136.6 KBCommission Agenda Summary September 2025 116.1 KBOctober 2025 Commission Meeting Minutes 148.4 KB

The Commission voted 4-0 on February 10, 2026 to approve a bond resolution authorizing an agreement with the Urban Redevelopment Agency to finance the project, with a bond issuance reported at $4,155,000, and approved the related bond paperwork authorizing the mayor to sign.

SourcesFebruary Minutes 197.2 KBCommission Agenda Summary February 2026 160.2 KB

Phase 2, construction of the amphitheater, went out for bid in April 2026, and on May 5, 2026 the Commission voted 3-0 to award the construction contract to Charles Black Construction, with amounts reported as $2,779,431 and $3,473,230. By July 2026 the contractor had begun work on the amphitheater's construction.

SourcesApril 2026 Commission Meeting Minutes 77.6 KBCommission Agenda Summary May 2026 146.3 KBMay City Commission Minutes 2026 80.4 KBJuly 2026 Comission Minutes 67.5 KB

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Approved
confirmed

Park Project change order for cast iron water line replacement on Martin Luther King/Clarkesville Street

recommends a change order to the contract with Higgins Construction in the amount of $178,220 to complete

Discussed
discussed

Downtown amphitheater project delayed by EPA issue

The amphitheater has run into a slight problem with EPA which will delay it slightly.

Approved
confirmed

Engineer's Recommendation for the Amphitheater Park Project

Engineer’s Recommendation for the Amphitheater Park Project Tab L Approved 4 - 0

Appeared on agenda
proposed

Engineer's Recommendation for the Amphitheater Park Project

Engineer’s Recommendation for the Amphitheater Park Project

Approved
confirmed

Bid award to Higgins Construction for Amphitheater Park Project Phase 1

Commissioner Bagwell made a motion to approve the bid from Higgins Construction of $1,833,489 and make an allowance of $200,000 for the restrooms

Showing 21–25 of 25 recorded steps.