IssueCorneliaapproved

Cornelia amphitheater contractor begins construction after bond financing and contract award

The city financed its long-running downtown amphitheater project with a bond through the Urban Redevelopment Agency and awarded the construction contract, and work is now underway on the park site.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

July 7, 2026: Amphitheater construction progress update

What happens next

No next step has been documented.

At a glance

What this means now

Where it stands

Phase 2, construction of the amphitheater, went out for bid in April 2026, and on May 5, 2026 the Commission voted 3-0 to award the construction contract to Charles Black Construction, with amounts reported as $2,779,431 and $3,473,230. By July 2026 the contractor had begun work on the amphitheater's construction.

The story

In January 2025 the Cornelia City Commission approved the engineer's recommendation for the Amphitheater Park Project and voted 4-0 to award the Phase 1 bid to Higgins Construction for $1,833,489, plus a $200,000 allowance for restrooms.

SourcesCommission Agenda Summary January 2025 127.9 KBJanuary 2025 City Commission Minutes 157.4 KB

The project hit a delay in February 2025 from an EPA issue. In May and July 2025 the Commission approved change orders with Higgins Construction to replace cast iron water lines on Martin Luther King Boulevard and Clarkesville Street, at amounts reported as $178,220 and $179,840.

Sources2025-Febuary-DDA- Minutes 1 1.2 MBCommission Agenda Summary May 2025 120.2 KBMay Minutes 2025 120.2 KB2nd Quarter Mintues 2025 Meeting 109.5 KB

Through the second half of 2025 the city worked on how to pay for the amphitheater itself, meeting to explore funding options and settling on a bond issued through the Urban Redevelopment Agency; the Commission voted 4-0 in September to approve a letter of intent with Raymond James for funding advisory services, with the bond process expected to take about 75 days. Parking on Clarkesville Street was installed and Grant Place and Martin Luther King were paved, and the Hospitality & Tourism Board reviewed the amphitheater design plans in August.

SourcesCity Manager's Monthly Report for August 2025 4.6 MBSeptember 2025 City Commission Minutes 136.6 KBCommission Agenda Summary September 2025 116.1 KBOctober 2025 Commission Meeting Minutes 148.4 KB

The Commission voted 4-0 on February 10, 2026 to approve a bond resolution authorizing an agreement with the Urban Redevelopment Agency to finance the project, with a bond issuance reported at $4,155,000, and approved the related bond paperwork authorizing the mayor to sign.

SourcesFebruary Minutes 197.2 KBCommission Agenda Summary February 2026 160.2 KB

Phase 2, construction of the amphitheater, went out for bid in April 2026, and on May 5, 2026 the Commission voted 3-0 to award the construction contract to Charles Black Construction, with amounts reported as $2,779,431 and $3,473,230. By July 2026 the contractor had begun work on the amphitheater's construction.

SourcesApril 2026 Commission Meeting Minutes 77.6 KBCommission Agenda Summary May 2026 146.3 KBMay City Commission Minutes 2026 80.4 KBJuly 2026 Comission Minutes 67.5 KB

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

mentioned
unknown

New city park construction (lighting, restrooms, epoxy floors, fencing)

Georgia Power has installed the new lights as well as the electrical meter.

Discussed
discussed

Park project construction progress (restrooms, concrete, lighting, Clarkesville/Grant Place/MLK paving)

The parallel parking on Clarkesville Street has been installed, and Grant Place and Martin Luther King have been paved.

Discussed
discussed

Amphitheater construction funding through bond process and ARC grant

The purpose of the meeting was to explore funding resources for the construction of the amphitheater. The bond process will take approximately 75 days to complete.

Discussed
discussed

Amphitheater construction progress update

The contractor has begun working on the construction of the Amphitheater.

Approved
confirmed

Recommendation for Amphitheater Contractor

Recommendation for Amphitheater Contractor Tab H Approved 3 - 0

Approved
confirmed

Amphitheater Project construction contract awarded to Charles Black Construction

Commissioner Reed made a motion to award Charles Black Construction the project, seconded by Commissioner Cook. Approved 3 - 0

Discussed
discussed

City park amphitheater (Phase 2) construction out for bid

Phase 2, which is the construction of the amphitheater is out for bid, we should be able to award this project at the May Commission meeting

Approved
confirmed

Bond Resolution authorizing agreement with Urban Redevelopment Agency to finance the Downtown Amphitheater Project

they will then issue the bond in the amount of $4.155,000.

Approved
confirmed

Bond paperwork for the Amphitheater Project

Bond Paperwork for Amphitheater Project Tab E Approved 4 – 0 to Authorize the Mayor sign the resolution

Appeared on agenda
proposed

Bond paperwork for the amphitheater project

Bond Paperwork for Amphitheater Project

Discussed
discussed

Amphitheater design review with Carter & Sloope

Commissioner Bagwell said it looks terrible and is something that a child would do.

Discussed
discussed

Amphitheater project bond financing exploration with Raymond James

The bond process will take approximately 75 days to complete.

Discussed
discussed

Bond financing for amphitheater construction through the Urban Redevelopment Agency

We feel that the best option is to do a bond through the Urban Redevelopment Agency.

Approved
confirmed

Letter of Intent with Raymond James

Letter of Intent with Raymond James Tab M Approved 4 - 0

Approved
confirmed

Letter of Intent with Raymond James for Amphitheater funding advisory services

Commissioner Cook made a motion to authorize the mayor to sign the letter of intent, seconded by Commissioner Griggs. Approved 4 – 0

Discussed
discussed

Bond financing for amphitheater construction through Urban Redevelopment Agency

the best option is to do a bond through the Urban Redevelopment Agency

Discussed
discussed

Amphitheater construction plans review

Dee Anderson brought the Amphitheater plans drawn up by the engineers working on it.The board members reviewed them with much appeal to the current plan.

Approved
confirmed

Clarkesville St. water line improvements for amphitheater/MLK project

MLK & Clarkesville water improvements approved by Commission for $179,840.00

Appeared on agenda
proposed

Park Project Change Order for Water Line Replacement

Park Project Change Order for Water Line Replacement

Approved
confirmed

Park project change order for water line replacement

Park Project Change Order for Water Line Replacement Approved 4 – 0

Showing 1–20 of 25 recorded steps.