Phase 2, construction of the amphitheater, went out for bid in April 2026, and on May 5, 2026 the Commission voted 3-0 to award the construction contract to Charles Black Construction, with amounts reported as $2,779,431 and $3,473,230. By July 2026 the contractor had begun work on the amphitheater's construction.
Cornelia amphitheater contractor begins construction after bond financing and contract award
The city financed its long-running downtown amphitheater project with a bond through the Urban Redevelopment Agency and awarded the construction contract, and work is now underway on the park site.
July 7, 2026: Amphitheater construction progress update
No next step has been documented.
At a glance
What this means now
The story
In January 2025 the Cornelia City Commission approved the engineer's recommendation for the Amphitheater Park Project and voted 4-0 to award the Phase 1 bid to Higgins Construction for $1,833,489, plus a $200,000 allowance for restrooms.
The project hit a delay in February 2025 from an EPA issue. In May and July 2025 the Commission approved change orders with Higgins Construction to replace cast iron water lines on Martin Luther King Boulevard and Clarkesville Street, at amounts reported as $178,220 and $179,840.
Through the second half of 2025 the city worked on how to pay for the amphitheater itself, meeting to explore funding options and settling on a bond issued through the Urban Redevelopment Agency; the Commission voted 4-0 in September to approve a letter of intent with Raymond James for funding advisory services, with the bond process expected to take about 75 days. Parking on Clarkesville Street was installed and Grant Place and Martin Luther King were paved, and the Hospitality & Tourism Board reviewed the amphitheater design plans in August.
The Commission voted 4-0 on February 10, 2026 to approve a bond resolution authorizing an agreement with the Urban Redevelopment Agency to finance the project, with a bond issuance reported at $4,155,000, and approved the related bond paperwork authorizing the mayor to sign.
Phase 2, construction of the amphitheater, went out for bid in April 2026, and on May 5, 2026 the Commission voted 3-0 to award the construction contract to Charles Black Construction, with amounts reported as $2,779,431 and $3,473,230. By July 2026 the contractor had begun work on the amphitheater's construction.
What happened
How this issue got here
Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.
mentionedunknownNew city park construction (lighting, restrooms, epoxy floors, fencing)
Georgia Power has installed the new lights as well as the electrical meter.
+
New city park construction (lighting, restrooms, epoxy floors, fencing)
Georgia Power has installed the new lights as well as the electrical meter.
DiscusseddiscussedPark project construction progress (restrooms, concrete, lighting, Clarkesville/Grant Place/MLK paving)
The parallel parking on Clarkesville Street has been installed, and Grant Place and Martin Luther King have been paved.
+
Park project construction progress (restrooms, concrete, lighting, Clarkesville/Grant Place/MLK paving)
The parallel parking on Clarkesville Street has been installed, and Grant Place and Martin Luther King have been paved.
DiscusseddiscussedAmphitheater construction funding through bond process and ARC grant
The purpose of the meeting was to explore funding resources for the construction of the amphitheater. The bond process will take approximately 75 days to complete.
+
Amphitheater construction funding through bond process and ARC grant
The purpose of the meeting was to explore funding resources for the construction of the amphitheater. The bond process will take approximately 75 days to complete.
DiscusseddiscussedAmphitheater construction progress update
The contractor has begun working on the construction of the Amphitheater.
+
Amphitheater construction progress update
The contractor has begun working on the construction of the Amphitheater.
ApprovedconfirmedRecommendation for Amphitheater Contractor
Recommendation for Amphitheater Contractor
Tab H Approved 3 - 0
+
Recommendation for Amphitheater Contractor
Recommendation for Amphitheater Contractor Tab H Approved 3 - 0
ApprovedconfirmedAmphitheater Project construction contract awarded to Charles Black Construction
Commissioner Reed made a motion to award Charles Black Construction the project,
seconded by Commissioner Cook. Approved 3 - 0
+
Amphitheater Project construction contract awarded to Charles Black Construction
Commissioner Reed made a motion to award Charles Black Construction the project, seconded by Commissioner Cook. Approved 3 - 0
DiscusseddiscussedCity park amphitheater (Phase 2) construction out for bid
Phase 2, which is the construction of the
amphitheater is out for bid, we should be able to award this project at the
May Commission meeting
+
City park amphitheater (Phase 2) construction out for bid
Phase 2, which is the construction of the amphitheater is out for bid, we should be able to award this project at the May Commission meeting
ApprovedconfirmedBond Resolution authorizing agreement with Urban Redevelopment Agency to finance the Downtown Amphitheater Project
they will then issue the bond in the amount
of $4.155,000.
+
Bond Resolution authorizing agreement with Urban Redevelopment Agency to finance the Downtown Amphitheater Project
they will then issue the bond in the amount of $4.155,000.
ApprovedconfirmedBond paperwork for the Amphitheater Project
Bond Paperwork for Amphitheater Project
Tab E Approved 4 – 0 to Authorize the Mayor sign the resolution
+
Bond paperwork for the Amphitheater Project
Bond Paperwork for Amphitheater Project Tab E Approved 4 – 0 to Authorize the Mayor sign the resolution
Appeared on agendaproposedBond paperwork for the amphitheater project
Bond Paperwork for Amphitheater Project
+
Bond paperwork for the amphitheater project
Bond Paperwork for Amphitheater Project
DiscusseddiscussedAmphitheater design review with Carter & Sloope
Commissioner Bagwell said it looks terrible
and is something that a child would do.
+
Amphitheater design review with Carter & Sloope
Commissioner Bagwell said it looks terrible and is something that a child would do.
DiscusseddiscussedAmphitheater project bond financing exploration with Raymond James
The bond process will take approximately 75 days to complete.
+
Amphitheater project bond financing exploration with Raymond James
The bond process will take approximately 75 days to complete.
DiscusseddiscussedBond financing for amphitheater construction through the Urban Redevelopment Agency
We feel that the best
option is to do a bond through the Urban Redevelopment Agency.
+
Bond financing for amphitheater construction through the Urban Redevelopment Agency
We feel that the best option is to do a bond through the Urban Redevelopment Agency.
ApprovedconfirmedLetter of Intent with Raymond James
Letter of Intent with Raymond James
Tab M Approved 4 - 0
+
Letter of Intent with Raymond James
Letter of Intent with Raymond James Tab M Approved 4 - 0
ApprovedconfirmedLetter of Intent with Raymond James for Amphitheater funding advisory services
Commissioner Cook made a motion to authorize the mayor to sign the letter of intent, seconded by Commissioner Griggs. Approved 4 – 0
+
Letter of Intent with Raymond James for Amphitheater funding advisory services
Commissioner Cook made a motion to authorize the mayor to sign the letter of intent, seconded by Commissioner Griggs. Approved 4 – 0
DiscusseddiscussedBond financing for amphitheater construction through Urban Redevelopment Agency
the best option is to do a bond through the
Urban Redevelopment Agency
+
Bond financing for amphitheater construction through Urban Redevelopment Agency
the best option is to do a bond through the Urban Redevelopment Agency
DiscusseddiscussedAmphitheater construction plans review
Dee Anderson brought the Amphitheater plans drawn up by the engineers working on
it.The board members reviewed them with much appeal to the current plan.
+
Amphitheater construction plans review
Dee Anderson brought the Amphitheater plans drawn up by the engineers working on it.The board members reviewed them with much appeal to the current plan.
ApprovedconfirmedClarkesville St. water line improvements for amphitheater/MLK project
MLK & Clarkesville water improvements approved by Commission for $179,840.00
+
Clarkesville St. water line improvements for amphitheater/MLK project
MLK & Clarkesville water improvements approved by Commission for $179,840.00
Appeared on agendaproposedPark Project Change Order for Water Line Replacement
Park Project Change Order for Water Line Replacement
+
Park Project Change Order for Water Line Replacement
Park Project Change Order for Water Line Replacement
ApprovedconfirmedPark project change order for water line replacement
Park Project Change Order for Water Line Replacement
Approved 4 – 0
+
Park project change order for water line replacement
Park Project Change Order for Water Line Replacement Approved 4 – 0
Showing 1–20 of 25 recorded steps.
Find a step on another page
These links also preserve bookmarks to earlier timeline steps.
- May 6, 2025: Park Project change order for cast iron water line replacement on Martin Luther King/Clarkesville Street
- February 4, 2025: Downtown amphitheater project delayed by EPA issue
- January 7, 2025: Engineer's Recommendation for the Amphitheater Park Project
- January 7, 2025: Engineer's Recommendation for the Amphitheater Park Project
- January 7, 2025: Bid award to Higgins Construction for Amphitheater Park Project Phase 1