IssueToccoaapproved

Toccoa commission approves bid and bond financing for Ritz Theatre expansion after geotechnical review

A downtown theater expansion moved from soil testing to a construction contract and bond financing, with recent talk of extra costs for bad dirt found at the site.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

August 31, 2026: Ritz Project update

What happens next

No next step has been documented.

At a glance

What this means now

Where it stands

Work has continued into 2026, with the commission considering bids for third-party inspections in March and later discussing pulling roughly $15,000 from contingency funds to address a bad dirt condition found during construction.

The story

The Toccoa City Commission discussed a geotechnical boring investigation at the Ritz Theatre expansion site in September 2025, part of early groundwork for the project.

SourcesToccoa City Commission Work Session - 09/22/2025 - 4:00pm MinutesToccoa City Commission Work Session Agenda 09/22/2025Toccoa City Commission Work Session - 09/22/2025 - 4:00pm Agenda

By November 2025, the commission was reviewing civil engineering and plumbing details for the project, with a contractor expected to provide pricing for consideration.

SourcesToccoa City Commission Work Session - 11/10/2025 - 4:00pm Minutes

Later that month, J Davis Construction submitted a formal base bid of $2,998,529 for the Ritz Theater annex, and the commission approved the bid for the expansion.

SourcesToccoa City Commission Work Session - 11/24/2025 - 3:30pm MinutesToccoa City Commission Meeting - 11/24/2025 - 5:00pm Minutes

In January 2026, the commission approved a bond agreement to help finance the expansion through the Downtown Development Authority, with Commissioner Jamieson opposed and Mayor Hellenga abstaining; the financing was reported finalized and closing the following month.

SourcesToccoa City Commission Meeting - 01/27/2026 - 5:00pm AgendaToccoa City Commission Meeting - 01/27/2026 - 5:00pm MinutesToccoa City Commission Meeting - 02/23/2026 - 5:00pm Minutes

Work has continued into 2026, with the commission considering bids for third-party inspections in March and later discussing pulling roughly $15,000 from contingency funds to address a bad dirt condition found during construction.

SourcesToccoa City Commission Called Meeting - 03/19/2026 - 11:00am AgendaToccoa City Commission Meeting - 05/11/2026 - 5:00pm Minutes

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Appeared on agenda
proposed

Ritz Project update

Update on the Ritz Project

Appeared on agenda
proposed

Ritz Project update

Update on the Ritz Project

Discussed
discussed

Ritz Theatre construction: contingency funds for bad dirt condition

we will be pulling some funding out of contingencies for bad dirt; the amount is around $15,000.00

Appeared on agenda
proposed

Bids for third-party inspections for the Ritz Addition

Consideration of Bids for Third Party Inspections for the Ritz Addition

Discussed
discussed

Ritz Theatre addition project and bond financing

The Bond financing will be finalized this week and should close on Thursday.

Appeared on agenda
proposed

Bond Agreement for the Ritz Expansion

Consideration of Bond Agreement for the Ritz Expansion

Approved
confirmed

Bond Agreement for the Ritz Theatre Expansion financed through Downtown Development Authority

A motion was made by Commissioner Carter, seconded by Commissioner Matheson to move forward with the Bond Agreement as submitted. Motion carried 3-1; Commissioner Jamieson opposed; Mayor Hellenga abstained.

Discussed
discussed

Ritz Theater annex expansion project and bond financing

J Davis Construction provided a formal base bid of $2,998,529 for construction of the Ritz Theater annex based on the current plans.

Appeared on agenda
proposed

Ritz Expansion

Consideration of the Ritz Expansion

Appeared on agenda
proposed

Ritz Theatre Expansion update

Update on the Ritz Expansion

Approved
confirmed

Bid for the Ritz expansion

A motion was made by Commissioner Fry, seconded by Commissioner Matheson to approve the bid for the Ritz expansion. Motion carried unanimously 3-2.

Appeared on agenda
proposed

Ritz Theatre Expansion project update

Update on the Ritz Expansion

Discussed
discussed

The Ritz theater civil engineering and plumbing update

the Civil Engineering should be back on Wednesday, plumbing changes and Civil Engineering; Jacob will be able to give a price for consideration.

Discussed
discussed

Geotechnical boring investigation at the Ritz Theatre expansion project

Discussion of Geotechnical Boring at the Ritz Theatre

Appeared on agenda
proposed

Geotechnical boring at the Ritz Theatre

Discussion of Geotechnical Boring at the Ritz Theatre

Appeared on agenda
proposed

Geotechnical boring at the Ritz Theatre

Discussion of Geotechnical Boring at the Ritz Theatre