Tallulah Falls advances Rails to Trails grant and a connected Public Safety Corridor project

The town accepted state trail funding requiring a local match and is separately funding road, drainage and bridge work on a connecting corridor using town safety funds and SPLOST dollars.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

May 27, 2026: SPLOST 6 reallocation toward bridge project

What happens next

No next step has been documented.

At a glance

What this means now

Where it stands

In November 2025 council approved $5,000 from Public Safety Funds for a survey of the corridor's bridge area. By May 2026, a councilperson was proposing directing roughly $78,000 in remaining SPLOST 6 funds toward the bridge work to bring it closer to a biddable amount, a step council had discussed but not yet voted on.

The story

In January 2025 the Downtown Development Authority voted unanimously to recommend accepting a GDOT Transportation Alternatives grant for the Rails to Trails/River Street project. The grant is an 80/20 match, with the town and DDA putting up $70,000; GDOT holds the funds rather than disbursing them directly to the town.

SourcesTallulah Falls Minutes - 01.16.25 RM Minutes - 01.16.25 RM Minutes.docxTallulah Falls Agendas - 02.13.25 RM Agenda Packet - 02.13.25 RM Agenda Packet.pdf

The following month, council took up a GDOT indemnification agreement tied to the grant, and the packet noted a separate Public Safety Corridor is planned within town that will connect to the trail corridor.

SourcesTallulah Falls Agendas - 02.13.25 RM Agenda - 02.13.25 RM Agenda.docxTallulah Falls Agendas - 03.13.25 RM Agenda Packet - 03.13.25 RM Agenda Packet.pdf

Through the spring, council discussed the Public Safety Corridor design project, estimated to cost between $750,000 and $1 million and covering a roundabout, sidewalks, culvert upgrades and paving. Conceptual design plans for the corridor were presented for public review in May.

SourcesTallulah Falls Agendas - 05.15.25 RM Agenda Packet - 05.15.25 RM Agenda Packet.pdfTallulah Falls Minutes - 04.17.25 BWS Minutes - 04.17.25 BWS Minutes.docxTallulah Falls Minutes - 05.15.25 RM Minutes - 05.15.25 RM Minutes.docxTallulah Falls Agendas - 06.12.25 RM Agenda Packet - 06.12.25 RM Agenda Packet.pdf

Council approved up to $65,000 from Public Safety Funds in July for a River Street storm pipe replacement tied to the corridor project, then in September approved a bid of $73,720 (up to $75,000) to award the work to a contractor.

SourcesTallulah Falls Minutes - 07.24.25 SCM Minutes - 07.24.25 SCM Minutes.docxTallulah Falls Minutes - 09.11.25 RM Minutes - 09.11.25 RM Minutes.docxTallulah Falls Agendas - 10.09.25 Agenda Packet - 20251009173742.pdf

In November 2025 council approved $5,000 from Public Safety Funds for a survey of the corridor's bridge area. By May 2026, a councilperson was proposing directing roughly $78,000 in remaining SPLOST 6 funds toward the bridge work to bring it closer to a biddable amount, a step council had discussed but not yet voted on.

SourcesTallulah Falls Minutes - 11.13.25 RM Minutes - 11.13.25 RM Minutes.docxTallulah Falls Agendas - 06.11.26 RM Agenda Packet - 06.11.26 RM Agenda Packet.pdfTallulah Falls Minutes - 05.27.26 BWS Minutes - 05.27.26 BWS Minutes.docx

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Appeared on agenda
proposed

Public Safety Initiative - Public Safety Corridor

PUBLIC SAFETY INITIATIVE - Public Safety Corridor

Discussed
discussed

SPLOST 6 fund reallocation toward bridge project

Councilperson Weatherly suggested directing the remaining SPLOST 6 funds that could be reallocated, approximately $78,000, toward the bridge project to help bring the project closer to a biddable amount.

Discussed
discussed

SPLOST 6 reallocation toward bridge project

directing the remaining SPLOST 6 funds that could be reallocated, approximately $78,000, toward the bridge project to help bring the project closer to a biddable amount

Appeared on agenda
proposed

Survey estimate for Safety Corridor Bridge area

Survey $5,000 Estimate Safety Corridor Bridge area VI. New Business

Approved
confirmed

Survey of safety corridor bridge area (Public Safety Funds)

Councilperson Weatherly requested approval from Public Safety Funds for $5,000 to complete the survey.

Appeared on agenda
proposed

Survey estimate for Safety Corridor Bridge area

F. Survey $5,000 Estimate – Safety Corridor Bridge area

Approved
confirmed

Safety Corridor pipe replacement bid, River Street

A motion to approve up to $75,000 for the project was made by Councilperson Franklin.

Appeared on agenda
proposed

Safety Corridor Pipe Replacement bid

Safety Corridor Pipe Replacement Bid $73,720

Appeared on agenda
proposed

Culvert installation project on River St by Higgins Construction Company

Culvert Installation for Tallulah Falls River St

Appeared on agenda
proposed

Safety Corridor Pipe Replacement bid award

Safety Corridor Pipe Replacement Bid $73,720

Approved
unknown

Safety Corridor pipe replacement bid

A motion to approve up to $75,000 for the project was made by Councilperson Franklin. The motion was seconded by Councilperson Augustine and unanimously approved.

Approved
confirmed

River Street storm pipe replacement funding (60-inch HDPE pipe, part of Safety Corridor Project)

A motion was made by Councilperson Augustine to approve up to $65,000 allocated from Public Safety Funds to be for the pipe replacement.

Appeared on agenda
proposed

Public Safety Corridor initiative

PUBLIC SAFETY INITIATIVE - Public Safety Corridor

Discussed
discussed

Safety corridor conceptual design plans

Councilperson Weatherly provided new conceptual design plans for the safety corridor for public review and scrutiny.

Discussed
discussed

Public Safety Corridor design project (roundabout, sidewalks, culvert upgrades, paving)

The project is estimated to cost between $750,000 and $1 million, including a roundabout, sidewalks, culvert upgrades, and paving.

Discussed
discussed

Public Safety Corridor design and construction project

The project is estimated to cost between $750,000 and $1 million, including a roundabout, sidewalks, culvert upgrades, and paving.

Appeared on agenda
proposed

GDOT Indemnification Agreement

GDOT Indemnification Agreement

Discussed
discussed

Rails to Trails project and proposed safety corridor

A separate safety corridor is planned within the city, which will connect to the trail corridor.

Discussed
discussed

DDA update on GDOT Transportation Alternatives grant funding for Rails to Trails/River Street project

DDA voted unanimously to recommend funding acceptance.

Discussed
discussed

DDA update on GDOT Transportation Alternatives (TA) project funding for Rails to Trails / River Street enhancement

DDA voted unanimously to recommend funding acceptance. o City and DDA do not receive the money; it is held by the GDOT. o 80/20 Grant with $70,000 match

Showing 1–20 of 22 recorded steps.

Find a step on another page

These links also preserve bookmarks to earlier timeline steps.

Research the record

Search the underlying agendas, minutes, and documents.

Search supporting records