Habersham County splits Fire/EMA/E911 headquarters building into two funding phases

Commissioners plan to use $4 million already budgeted to start the new fire, EMA and 911 headquarters now, pushing a second phase to a future SPLOST round.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

June 16, 2025: Fire/EMA/E911 Headquarters construction funding, Phase I/Phase II under SPLOST VIII

What happens next

No next step has been documented.

At a glance

What this means now

Where it stands

By a June 16, 2025 work session, commissioners were discussing using the $4 million already budgeted for the project to fund a "Phase I," with a "Phase II" to be included on a future SPLOST VIII list.

The story

A draft SPLOST VIII project list proposed $11 million in recommended funding, against a $12 million request, for Phase II of the Central Base Fire/EMS/911 Building.

Sources31 Draft of SPLOST VIII Project List 07.09

The Habersham County Board of Commissioners' FY2025 budget report said bids had been issued and an award made to Sunbelt Builders Inc. for the Animal Control and Fire/EMS/911 Headquarters buildings. The same report noted a separate E-911 project funded under SPLOST VII, awarded in FY23, was 50% complete.

Sourcescounty-habersham-fy2025-budget-report.pdf

At a February 13, 2025 planning retreat, Capital Projects Manager Jerry Baggett gave commissioners a status update on the Fire/EMA/E911 Headquarters project.

SourcesMeeting4882_9 Minutes for BOC 02.13.25 Planning Retreat.pdfMinutes for BOC 02.13.25 Planning Retreat

By a June 16, 2025 work session, commissioners were discussing using the $4 million already budgeted for the project to fund a "Phase I," with a "Phase II" to be included on a future SPLOST VIII list.

SourcesMeeting5085_4 Minutes for 06.16.25 BOC Work Session.pdf

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Appeared on agenda
proposed

Phase II of the Central Base Fire/EMS/911 Building

Phase II of Central Base Fire/EMS/911 Building 11,000,000.00$ 12,000,000.00$

Discussed
discussed

Fire/EMA/E911 Headquarters construction funding, Phase I/Phase II under SPLOST VIII

using the $4 million that was budgeted for this project for a “Phase I” while including “Phase Il” on future SPLOST VILL

Discussed
discussed

Fire/EMA/E911 Headquarters SPLOST project status

Fire/EMA/E911 Headquarters Jerry Baggett, Capital Projects Manager

Discussed
discussed

Status update on SPLOST-funded Fire/EMA/E911 Headquarters project

Fire/EMA/E911 Headquarters Jerry Baggett, Capital Projects Manager

Approved
unknown

Construction award for Animal Control and Fire/EMS/911 Headquarters buildings

have been issued and an award made to Sunbelt Builders Inc.

Approved
unknown

E-911 project (SPLOST VII)

911 project was awarded in FY23 and is 50% complete at this time.