NEGAbriefLocal records made useful
IssueFranklin Countyunder consideration

Georgia EPD recommends air permit for Ellenwood data center's backup generators

The draft permit sets nitrogen oxide and other emission limits for diesel emergency generators at a Clayton County data center project, and drew objection from the Sierra Club during public comment.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

October 23, 2026: Synthetic minor permit for TADG - ATL02 / Ellenwood data center

What happens next

No next step has been documented.

At a glance

What this means now

Where it stands

EPD issued a further notice on October 23, 2026 proposing a synthetic minor permit for the same Ellenwood data center project.

The story

Georgia's Environmental Protection Division drafted an air quality permit for diesel-fired emergency generators at a data center project by TADG (ATL02) in Ellenwood, Clayton County. The draft set a facility-wide notification threshold of 99 tons of nitrogen oxide emissions per rolling 12-month period, a monthly threshold of 8.25 tons, and limits on generator run hours, including up to 200 hours per year of operation and 100 hours per year for maintenance and testing.

Sources30104 draft

A public comment period on the draft permit ended May 1, 2026, with comments submitted by the Sierra Club.

Sources30104 nar

On April 30, 2026, EPD's Air Protection Branch recommended that Permit No. 7375-063-0154-S-01-0 be issued for construction and operation of the diesel-fired emergency generators, with a facility-wide limit of 99 tons per year of nitrogen oxide and a 100-hour-per-year limit for maintenance and readiness testing.

Sources30104 nar

EPD issued a further notice on October 23, 2026 proposing a synthetic minor permit for the same Ellenwood data center project.

SourcesPA0926-4 (1)

Scheduled

What is on the calendar

Dated steps the official record has already set. They move into the timeline below once they happen.

Appeared on agenda
proposed

Draft permit condition setting 12-month rolling NOx emission notification threshold of 99 tons for emergency generators

exceeds 99 tons for the emergency generator s

Appeared on agenda
proposed

Air Quality Permit for TADG – ATL02/Ellenwood data center emergency standby generators

Construction and operation of a data center consisting of emergency standby stationary generators.

Appeared on agenda
proposed

Draft permit condition setting monthly NOx emission notification threshold of 8.25 tons for emergency generators

monthly total combined NOx emissions for the emergency generators exceeds 8.25 tons

Appeared on agenda
proposed

Synthetic minor permit for TADG - ATL02 / Ellenwood data center

Construct and operate an advanced technology ecosystem data center.

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Discussed
discussed

Public comment period on draft air permit for TADG – ATL02/Ellenwood emergency generators

The Public Advisory period ended on May 1, 2026, with comments received from Sierra Club.

Appeared on agenda
proposed

Air permit application for TADG – ATL02 data center diesel emergency generators in Ellenwood, Clayton County

I recommend that Permit No. 7375-063-0154-S-01-0 be issued to TADG – ATL02 / Ellenwood

Appeared on agenda
proposed

Air quality permit for diesel-fired emergency generators at TADG – ATL02 data center, Ellenwood (Clayton County)

I recommend that Permit No. 7375-063-0154-S-01-0 be issued to TADG – ATL02 / Ellenwood for the construction and operation of diesel-fired emergency generators