Cornelia water authority keeps reviewing $33.56 million estimate for wastewater plant expansion

The authority has discussed a cost estimate to expand the wastewater treatment plant to 4.5 million gallons per day across four meetings without recording a vote.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

April 28, 2026: WWTP Expansion to 4.5 MGD

What happens next

No next step has been documented.

The story

In January 2025, the Cornelia Water & Sewerage Authority discussed the plant expansion, noting structural design was about 95% complete, electrical design about 75% complete, and overall project design about 95% complete. The discussion referenced a possible 325% tipping fee increase.

Sources4th Quarter Mintues 2024 Meeting 108.8 KBCornelia Water & Sewerage Authority Meeting Agenda for April 22 194.8 KB

By July 2025, the authority discussed that 90%-complete plans had been sent to Reeves-Young for cost estimating in March 2025, producing an estimate of $33.56 million, plus or minus 10%. Other figures discussed included $16.09 million plus or minus 10%, a range of plus or minus $10 million, and $2 million.

Sources2nd Quarter Mintues 2025 Meeting 109.5 KB

The authority discussed the same March 2025 cost estimate again in January 2026, still citing the $33.56 million figure plus or minus 10%, along with additional cost figures including $2,300,000, $23,000,000, $150,000, and $800,000.

SourcesCornelia Water & Sewer Authority 4th Quarter Mintues 2025 153.2 KB2) Cornelia Water Authority Agenda for April 28, 2026 180.1 KB

As of the authority's April 2026 meeting, the expansion cost estimate of $33.56 million plus or minus 10% and the related cost figures were discussed again, with no vote recorded on the project.

Sources1ST Quarter Mintues 2026 Water Authority 286.5 KB

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Discussed
discussed

WWTP Expansion to 4.5 MGD

90% plans sent to Reeves-Young in March for cost estimating, $33.56 million ±10%

Discussed
discussed

WWTP Expansion to 4.5 MGD

90% plans sent to Reeves-Young in March for cost estimating, $33.56 million ±10%

Discussed
discussed

WWTP Expansion to 4.5 MGD

90% plans sent to Reeves-Young in March for cost estimating, $33.56 million

Discussed
discussed

WWTP Expansion to 4.5 MGD

90% complete plants sent to Reeves-Young for cost estimating, $33.56 million ±10% in March 2025

Discussed
discussed

WWTP Expansion to 4.5 MGD

Structural design is about 95% complete; electrical design is about 75% complete; overall project design is about 95% complete.

Discussed
discussed

WWTP Expansion to 4.5 MGD

Structural design is about 95% complete; electrical design is about 75% complete; overall project design is about 95% complete.