Cornelia water authority tracks Hazel Creek Dam repairs, eyes October construction start

Repairs to a dam and reservoir that serve the city's water system have cleared a state safety review, with work timed to low water levels this fall.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

April 28, 2026: Hazel Creek Dam No. 7 / Camp Creek Reservoir repairs

What happens next

Construction is planned to start in October, timed with low water levels in the reservoir.

At a glance

What this means now

Where it stands

The authority's April 2026 minutes repeated that Safe Dams approval had been received and that construction was still planned for an October start.

The story

The Cornelia Water & Sewerage Authority has been discussing repairs to Hazel Creek Dam No. 7 and the Camp Creek Reservoir, including replacing the gate valve and trash rack and rehabilitating the outlet pipe with a cured-in-place pipe liner.

Sources4th Quarter Mintues 2024 Meeting 108.8 KBCornelia Water & Sewerage Authority Meeting Agenda for April 22 194.8 KB

The authority discussed the same repair plan again at its July 2025 meeting.

Sources2nd Quarter Mintues 2025 Meeting 109.5 KB

By January 2026, the authority reported that approval had been received from the state Safe Dams program, with construction planned to start in October to coincide with low water levels in the reservoir.

Sources2) Cornelia Water Authority Agenda for April 28, 2026 180.1 KBCornelia Water & Sewer Authority 4th Quarter Mintues 2025 153.2 KB

The authority's April 2026 minutes repeated that Safe Dams approval had been received and that construction was still planned for an October start.

Sources1ST Quarter Mintues 2026 Water Authority 286.5 KB

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Discussed
discussed

Hazel Creek Dam No. 7 / Camp Creek Reservoir repairs

Approval from Safe Dams Received. Construction start in October to be timed with low water level in reservoir

Discussed
discussed

Hazel Creek Dam No. 7/Camp Creek Reservoir Repairs

Approval from Safe Dams Received. Construction start in October to be timed with low water

Discussed
discussed

Hazel Creek Dam No. 7/Camp Creek Reservoir Repairs

Approval from Safe Dams Received. Construction start in October to be timed with low water

Discussed
discussed

Hazel Creek Dam No. 7 / Camp Creek Reservoir repairs

Gate valve to be replaced and trash rack to be replaced, outlet pipe to be rehabilitated with CIPP

Discussed
discussed

Hazel Creek Dam No. 7/Camp Creek Reservoir Repairs

Gate valve to be replaced and trash rack to be replaced, outlet pipe to be rehabilitated with CIPP

Discussed
discussed

Hazel Creek Dam No. 7/Camp Creek Reservoir repairs

Gate valve to be replaced and trash rack to be replaced, outlet pipe to be rehabilitated with CIPP