With that extended deadline approaching, an item to extend the moratorium barring acceptance of data center land use applications appears on the board's October 13, 2026 agenda packet.
Stephens County commissioners weigh extending data center application freeze again
The county's moratorium on accepting new land-use applications for data centers is set to expire October 14, and commissioners have an extension before them again.
The Board of Commissioners is scheduled to take up a further extension of the moratorium at its October 13, 2026 meeting, ahead of the current moratorium's October 14, 2026 expiration.
At a glance
What this means now
The story
On April 14, 2026, the Stephens County Board of Commissioners unanimously approved a resolution imposing a moratorium barring the acceptance of land use applications for data centers, effective immediately and running through July 14, 2026.
A resolution to lift that moratorium appeared on the board's April 28, 2026 agenda, but no commissioner made a motion on it, and the item remained for discussion only.
The board instead voted unanimously on May 26, 2026, on a motion by Commissioner Simmons, to extend the moratorium by three months, to October 14, 2026.
With that extended deadline approaching, an item to extend the moratorium barring acceptance of data center land use applications appears on the board's October 13, 2026 agenda packet.
What happened
How this issue got here
Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.
Appeared on agendaproposedExtension of moratorium on land use applications for data centers
EXTEND MORATORIUM BARRING THE ACCEPTANCE OF LAND USE APPLICATIONS FOR DATA CENTERS
+
Extension of moratorium on land use applications for data centers
EXTEND MORATORIUM BARRING THE ACCEPTANCE OF LAND USE APPLICATIONS FOR DATA CENTERS
ApprovedconfirmedExtension of moratorium barring land use applications for data centers
Extension for moratorium barring the acceptance of land use applications for data centers.
Motion to approve: Commissioner Simmons
+
Extension of moratorium barring land use applications for data centers
Extension for moratorium barring the acceptance of land use applications for data centers. Motion to approve: Commissioner Simmons
ApprovedunknownExtension of moratorium barring acceptance of land use applications for data centers
explained it would be another three (3) months — to October 14, 2026.
+
Extension of moratorium barring acceptance of land use applications for data centers
explained it would be another three (3) months — to October 14, 2026.
DiscusseddiscussedResolution to lift the moratorium barring acceptance of land use applications for data centers
Since no motion was made on the item, this item remains for discussion only.
+
Resolution to lift the moratorium barring acceptance of land use applications for data centers
Since no motion was made on the item, this item remains for discussion only.
DiscusseddiscussedResolution to lift moratorium barring acceptance of land use applications for data centers
Adoption of Resolution to lift moratorium barring the acceptance of land use applications for
data centers.
Motion: None
+
Resolution to lift moratorium barring acceptance of land use applications for data centers
Adoption of Resolution to lift moratorium barring the acceptance of land use applications for data centers. Motion: None
Appeared on agendaproposedResolution to lift moratorium barring acceptance of land use applications for data centers
Adoption of Resolution to lift moratorium barring the acceptance of land use applications for
+
Resolution to lift moratorium barring acceptance of land use applications for data centers
Adoption of Resolution to lift moratorium barring the acceptance of land use applications for
ApprovedconfirmedResolution for a moratorium on accepting land use applications for data centers
Resolution for a moratorium barring the acceptance of land use applications for data centers.
+
Resolution for a moratorium on accepting land use applications for data centers
Resolution for a moratorium barring the acceptance of land use applications for data centers.
ApprovedconfirmedResolution imposing a moratorium on land use applications for data centers
a moratorium is imposed through and including July 14, 2026, with said moratorium being effective
immediately, such that no land use applications for data centers shall be accepted
+
Resolution imposing a moratorium on land use applications for data centers
a moratorium is imposed through and including July 14, 2026, with said moratorium being effective immediately, such that no land use applications for data centers shall be accepted
Appeared on agendaproposedResolution for a moratorium barring acceptance of land use applications for data centers
Resolution for a moratorium barring the acceptance of land use applications for data centers
+
Resolution for a moratorium barring acceptance of land use applications for data centers
Resolution for a moratorium barring the acceptance of land use applications for data centers
Appeared on agendaproposedMoratorium on acceptance of land use applications for data centers
MOTION TO ADOPT A
RESOLUTION CALLING FORA
MORATORIUM BARRING THE
ACCEPTANCE OF LAND USE
APPLICATIONS FOR DATA
CENTERS PURSUANT TO THE
ZONING REGULATIONS OF
STEPHENS COUNTY,
GEORGIA AND AUTHORIZE
CHAIRMAN TO SIGN
RESOLUTION.
+
Moratorium on acceptance of land use applications for data centers
MOTION TO ADOPT A RESOLUTION CALLING FORA MORATORIUM BARRING THE ACCEPTANCE OF LAND USE APPLICATIONS FOR DATA CENTERS PURSUANT TO THE ZONING REGULATIONS OF STEPHENS COUNTY, GEORGIA AND AUTHORIZE CHAIRMAN TO SIGN RESOLUTION.