Several pieces of the work are documented as completed: the regulator station and the initial roughly 12% pressure increase were reported in December, and the new line segment cited in April had been pressure-tested. The broader project, however, was not described as finished. Its reported progress rose from about 60% in December to about 85% in April, both described as on schedule. The 25% total-capacity figure was a target tied to a planned second pressure increase, not a confirmed result.
Royston’s $6 million gas-pressure project is 85% complete, city says
After a new regulator station was finished and a section of new line passed pressure testing, construction remains unfinished and a planned second pressure increase has not been confirmed.
The next meaningful public milestone is a later city record showing whether the remaining construction was completed and whether the second pressure increase took place. No final completion update appears in the records through April 21, 2026, and no date is given for the unfinished work. Residents can therefore see substantial construction and testing reported, but not yet a documented conclusion to the full pressure-improvement project or confirmation of its intended 25% total capacity growth.
At a glance
What this means now
The story
Royston’s $6,025,471.61 Natural Gas Pressure Improvement Project was about 85% complete and on schedule as of April 21, 2026, City Manager reports said. The city had pressure-tested new line running from Hill Street to near the Highway 145 intersection in Franklin Springs, marking progress on a project intended to strengthen gas pressure across an area extending through Franklin Springs and along Highway 145.
The project is a major utility investment for Royston: City officials have described its high-school-area regulator station and related line work as a way to increase supply-side gas pressure. In December, the city said the first main-line pressure increase from Bowman had raised pressure by about 12%, while a further increase was intended to bring total capacity growth to 25%. Whether that second step occurred remains unresolved in the city records through April.
The work moved from planning to construction over 2025. In January, Royston said it had hired Carter & Sloope to manage the bid process while designing and preparing to build a regulator station near Franklin County High School. Council then approved $19,326 in station materials in February. After bids were opened June 17, council unanimously awarded Southern Pipeline LLC the larger construction contract on July 8; a notice of award followed by August, when the city said the station had been constructed and was ready for installation.
City Council set the project in motion through its materials approval and its 6-0 contract vote, while the city’s operations reports have provided the public progress updates. Southern Pipeline LLC is the contractor selected for the $6 million project. The city has reported that the high-school regulator station was complete by December and that work was then concentrated in Franklin Springs and northwest along Highway 145; the records do not include a separate public statement from Southern Pipeline or from affected residents.
Several pieces of the work are documented as completed: the regulator station and the initial roughly 12% pressure increase were reported in December, and the new line segment cited in April had been pressure-tested. The broader project, however, was not described as finished. Its reported progress rose from about 60% in December to about 85% in April, both described as on schedule. The 25% total-capacity figure was a target tied to a planned second pressure increase, not a confirmed result.
The next meaningful public milestone is a later city record showing whether the remaining construction was completed and whether the second pressure increase took place. No final completion update appears in the records through April 21, 2026, and no date is given for the unfinished work. Residents can therefore see substantial construction and testing reported, but not yet a documented conclusion to the full pressure-improvement project or confirmation of its intended 25% total capacity growth.
Arguments in the record
Positions presented publicly
City records describe the regulator station and line work as measures to increase gas supply-side pressure and capacity.
Southern Pipeline LLC received the council-approved construction contract; the records do not include the company’s own public account of progress or remaining work.
What happened
How this issue got here
Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.
mentionedconfirmedProject reported about 85% complete after pressure testing
On April 21, 2026, the city manager reported the project was about 85% complete and on schedule, with the new line pressure-tested from Hill Street to near the Highway 145 intersection in Franklin Springs.
+
Project reported about 85% complete after pressure testing
On April 21, 2026, the city manager reported the project was about 85% complete and on schedule, with the new line pressure-tested from Hill Street to near the Highway 145 intersection in Franklin Springs.
mentionedconfirmedPressure-improvement project reported about 60% complete
The December 2025 operations report said work on the 2025 Pressure Improvement Project was about 60% complete, on schedule, and concentrated in Franklin Springs and northwest along Highway 145.
+
Pressure-improvement project reported about 60% complete
The December 2025 operations report said work on the 2025 Pressure Improvement Project was about 60% complete, on schedule, and concentrated in Franklin Springs and northwest along Highway 145.
CompletedconfirmedHigh-school regulator station completed; first pressure increase made
A December 9, 2025 operations report said work had progressed into Franklin Springs, the high-school regulator station was completed, and the first Transco main-line pressure increase from Bowman raised pressure about 12%; a second increase was planned to bring total capacity growth to 25%.
+
High-school regulator station completed; first pressure increase made
A December 9, 2025 operations report said work had progressed into Franklin Springs, the high-school regulator station was completed, and the first Transco main-line pressure increase from Bowman raised pressure about 12%; a second increase was planned to bring total capacity growth to 25%.
CompletedconfirmedHigh-school regulator station constructed and ready for installation
An August 12, 2025 operations report stated that the new pressure-regulator station planned near the high school had been constructed and was ready for installation.
+
High-school regulator station constructed and ready for installation
An August 12, 2025 operations report stated that the new pressure-regulator station planned near the high school had been constructed and was ready for installation.
ExecutedconfirmedNotice of award issued; pre-construction meeting scheduled
An August 12, 2025 operations report said a notice of award had been tendered to Southern Pipeline LLC and that a pre-construction meeting was scheduled for August.
+
Notice of award issued; pre-construction meeting scheduled
An August 12, 2025 operations report said a notice of award had been tendered to Southern Pipeline LLC and that a pre-construction meeting was scheduled for August.
ApprovedconfirmedCouncil awarded $6.03 million pressure-improvement contract
On July 8, 2025, council voted 6-0 to award Southern Pipeline LLC a $6,025,471.61 contract for the 2025 Natural Gas Pressure Improvement Project.
+
Council awarded $6.03 million pressure-improvement contract
On July 8, 2025, council voted 6-0 to award Southern Pipeline LLC a $6,025,471.61 contract for the 2025 Natural Gas Pressure Improvement Project.
Appeared on agendaproposed$6.03 million gas-pressure contract placed before city
A July 2025 agenda put a proposed $6,025,471.61 award to Southern Pipeline LLC for the 2025 Natural Gas Pressure Improvement Project before city officials; the bid opening had occurred June 17, 2025.
+
$6.03 million gas-pressure contract placed before city
A July 2025 agenda put a proposed $6,025,471.61 award to Southern Pipeline LLC for the 2025 Natural Gas Pressure Improvement Project before city officials; the bid opening had occurred June 17, 2025.
Appeared on agendaconfirmedCity began bid process for 2025 gas-capacity expansion
A January operations report said the city had contracted with Carter & Sloope for the bid process and was working to design, build, and install a regulator station near the high school.
+
City began bid process for 2025 gas-capacity expansion
A January operations report said the city had contracted with Carter & Sloope for the bid process and was working to design, build, and install a regulator station near the high school.
ApprovedconfirmedCouncil approved $19,326 in regulator-station materials
Council approved $19,326 in materials to construct a regulator station near Franklin County High School to increase gas supply-side line pressure, as part of a broader purchase motion that passed 5-0.
+
Council approved $19,326 in regulator-station materials
Council approved $19,326 in materials to construct a regulator station near Franklin County High School to increase gas supply-side line pressure, as part of a broader purchase motion that passed 5-0.
Still unresolved
What is not yet known
These are evidence gaps, not assumptions. They remain open until a dependable source closes them.
- City records reviewed through April 21, 2026 do not document final completion of the broader pressure-improvement project.
- The city described a second pressure increase as planned in December 2025, but those records do not confirm that it occurred.
Newsroom notes1 open check on the record
How the newsroom is still working this matter. These are process notes, not reported facts.
- outcome checkThe official record of the April 21, 2026 meeting lists this item; as of September 3, 2026 it was checked and no vote or other recorded action on this specific item was identified in it.Check the official sources again on October 3, 2026.