Lavonia council approves borrowing up to $5 million for water plant Phase II

The city is moving ahead with a multi-phase overhaul of its water treatment plant, backed by state loans, after earlier discussing a joint water plant with Franklin County and the Hart County Water Authority.

By NEGA Brief NewsroomLast checked September 30, 2026
Latest

August 3, 2026: GEFA Phase II resolution to borrow up to $5,000,000 for water plant upgrade

What happens next

No next step has been documented.

At a glance

What this means now

Where it stands

In August 2026, the council unanimously approved a resolution authorizing the city to borrow up to $5,000,000 from the Georgia Environmental Finance Authority (GEFA) to finance Phase II of the water plant upgrade.

The story

In November 2025, Lavonia's mayor addressed a potential Memorandum of Understanding among the City of Lavonia, the Franklin County Board of Commissioners, and the Hart County Water Authority concerning construction of a large-scale water treatment plant.

SourcesMinutes

By April 2026, the council was discussing taste and odor issues in Lavonia's own water system, which sometimes creates an earthy smell, and visited an Anderson County water treatment facility to look at potential solutions.

SourcesMinutes

In May 2026, the council discussed a water plant capacity upgrade planned in phases, with Phase 1 and Phase 2 each described as $5 million projects carrying about $4 million in loan forgiveness built into each.

SourcesMinutes

Bids for Phase 1 were set to open June 16, and by July the city had selected Sol Construction, LLC, a contractor with an established prior working relationship with the city, to complete Phase 1 of the water plant improvements.

SourcesMinutesMinutes

In August 2026, the council unanimously approved a resolution authorizing the city to borrow up to $5,000,000 from the Georgia Environmental Finance Authority (GEFA) to finance Phase II of the water plant upgrade.

SourcesMinutes

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Appeared on agenda
proposed

GEFA Phase II update

GEFA – Phase II update

Approved
confirmed

GEFA Phase II resolution to borrow up to $5,000,000 for water plant upgrade

Mayor Umbehant presented a resolution authorizing the City of Lavonia to borrow up to $5,000,000 from Georgia Environmental Finance Authority (GEFA) to finance Phase II of the water plant upgrade.

Discussed
discussed

Water Treatment Plant Phase 1 bid award to Sol Construction, LLC

The City has selected Sol Construction, LLC, which has an established prior working relationship with the city, to complete Phase 1 of the water treatment plant improvements.

Discussed
discussed

Water Treatment Plant Phase 1 project bidding

will be opened on June 16 at 10:00 AM.

Discussed
discussed

Water plant capacity upgrade project, Phases 1-3

Phase 1 and Phase 2 are each $5 million projects with approximately $4 million in loan forgiveness built into each

Discussed
discussed

Water taste/odor issue in Lavonia's water system; council visit to Anderson County water treatment facility for potential solutions

to address taste and odor issues in Lavonia's water system that sometimes creates an earthy smell.

Discussed
discussed

Mayor's remarks on potential Memorandum of Understanding among City of Lavonia, Franklin County, and Hart County Water Authority for a large-scale water treatment plant

I want to address the potential Memorandum of Understanding between the City Lavonia, the Franklin Co. BOC, and the Hart County Water Authority concerning the building of a large-scale water treatment plant.