Habersham approves private airport-hangar leases, but construction remains unconfirmed

Two builders received 20-year ground leases for planned hangars at Habersham County Airport; the county still has no documented start date, completed buildings or signed leases.

By NEGA Brief Newsroom

Story history

Updates and corrections

Earlier published versions remain available here. The civic timeline below records what government did; this archive records how our published account changed.

  1. Updated

    Habersham approves two private airport-hangar leases, with buildout still unconfirmed

    The published Issue changed after new evidence or editorial review.

    Read version 2
  2. Updated

    Habersham approves two private airport-hangar leases, with buildout still unconfirmed

    Initial durable snapshot of the published Issue.

    Read version 1

At a glance

What this means now

Where it stands

The county has approved the two leases and instructed that the remaining sites be readvertised; those are completed governmental actions. Private construction, county electrical work and eventual transfer of the hangars to county ownership are terms of the approved arrangement, not documented completed acts. The estimated $450,000 combined value and projected revenue are estimates recorded in the July minutes, not realized results. The public record also does not establish a construction start, completion, occupancy, lease payment or whether proposed Georgia Department of Transportation support for site preparation was requested or awarded.

The story

Habersham County Commission unanimously approved two 20-year ground leases July 15, 2024, allowing Charles Brammer Jr. and FBO Drive to build private hangars at Habersham County Airport. The leases cover two of four planned 60-by-60-foot sites, and commissioners directed that the other two sites be readvertised. The action is the latest confirmed step in the county’s effort to add hangar space, but the minutes do not show that either lease was signed or that construction began.

SourcesMeeting4315_3 Minutes for 07.15.24 BOC Regular Meeting.pdfMinutes for 07.15.24 BOC Regular Meeting

The arrangement would put the upfront cost of the buildings on the private lessees while giving the county a future ownership interest: officials said the hangars would revert to Habersham County after the 20-year terms. For airport users, the central question is whether the approved sites become usable hangar space. For taxpayers, the stakes include the county’s limited stated responsibility for electricity, possible site-preparation costs and whether projected rental, tax and fuel-sales revenue ever materializes.

SourcesMeeting4315_3 Minutes for 07.15.24 BOC Regular Meeting.pdfMinutes for 07.15.24 BOC Regular MeetingMeeting3931_Approved Minutes - August 10, 2023 Regular Meeting.pdf

The proposal grew from a May 2023 Airport Commission discussion of public-private hangar development, when officials cited 74 based aircraft and said two 10-unit T-hangars could increase that number to 94. By June, the commission was considering an RFP under which an interested party would build to airport-developed plans. It then explored a possible state funding request for site preparation, refined a four-site ground-lease concept and worked through proposal scoring and conflict safeguards. Review of the RFP and lease was tabled into early 2024 before officials discussed reissuing it in June with a 20-year, rather than 25-year, term.

SourcesMeeting3928_Approved Minutes - May 11- 2023 Regular Meeting.pdfMeeting4264_Approved Minutes - October 12- 2023 Work Session.pdfMeeting4197_Approved Minutes - June 5- 2023 Work Session.pdfMeeting3931_Approved Minutes - August 10, 2023 Regular Meeting.pdf

County and airport officials framed the leases as a way to obtain privately financed hangars while the county’s stated cost would be running electricity to the sites. The July minutes describe an estimated combined $450,000 hangar value that would revert to the county at lease end, along with possible annual rent, tax and fuel-sales revenue. Prospective builders were expected to finance construction, and the commission had earlier discussed evaluating proposals on minimum monthly rent, financial plan, economic impact, qualifications, experience and capital investment. Officials also contemplated a separate scoring group because airport board members could submit proposals.

SourcesMeeting4315_3 Minutes for 07.15.24 BOC Regular Meeting.pdfMinutes for 07.15.24 BOC Regular MeetingMeeting4384_AGENDA - Airport Commission Meeting 6-11-24.pdfMeeting4384_Approved Minutes - June 11- 2024 Regular Meeting.pdf

The county has approved the two leases and instructed that the remaining sites be readvertised; those are completed governmental actions. Private construction, county electrical work and eventual transfer of the hangars to county ownership are terms of the approved arrangement, not documented completed acts. The estimated $450,000 combined value and projected revenue are estimates recorded in the July minutes, not realized results. The public record also does not establish a construction start, completion, occupancy, lease payment or whether proposed Georgia Department of Transportation support for site preparation was requested or awarded.

SourcesMeeting4315_3 Minutes for 07.15.24 BOC Regular Meeting.pdfMinutes for 07.15.24 BOC Regular MeetingMeeting3931_Approved Minutes - August 10, 2023 Regular Meeting.pdf

The next public sign of movement would be a later Airport Commission or County Commission record showing that the leases were executed and identifying responsibility, funding and timing for paving, site preparation or electrical service. A new procurement notice or meeting action could also show whether the two unassigned sites are offered again or awarded. Until then, it remains undecided how many hangars will actually be built, when airport users could use them and whether any outside support will help prepare the sites.

SourcesMeeting4315_3 Minutes for 07.15.24 BOC Regular Meeting.pdfMinutes for 07.15.24 BOC Regular MeetingMeeting3931_Approved Minutes - August 10, 2023 Regular Meeting.pdf

Arguments in the record

Positions presented publicly

County and airport officials

Officials described a private-build arrangement in which the county would run electricity, the lessees would build the hangars and the facilities would revert to county ownership after 20 years.

Implementation status

The approval does not establish that the leases were signed, that construction started or that any new hangar space is available.

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Approved
confirmed

Commission approved two private hangar ground leases

On July 15, 2024, the Commission unanimously approved 20-year ground leases for Charles Brammer Jr. and FBO Drive to build hangars on two of four 60-by-60-foot sites and directed readvertising of the remaining two. The builders would fund construction; the stated county cost was running electricity. The minutes project about $450,000 in combined hangar value reverting to county ownership after 20 years, plus potential annual rental, tax, and fuel-sales revenue.

Discussed
discussed

Commission discussed reissuing a 20-year hangar RFP

On June 11, 2024, officials discussed reissuing the RFP with a 20-year lease term rather than 25 years. The scoring summary included a $360 minimum monthly rent, financial plan, economic impact, qualifications and experience, and capital investment.

Tabled
confirmed

Hangar RFP and ground lease carried forward

The February 13, 2024 agenda listed the 60-by-60-foot hangar RFP and new ground lease as tabled from the January 9 meeting and scheduled them for further review.

Appeared on agenda
proposed

Commission scheduled review of hangar RFP and ground lease

The January 9, 2024 agenda scheduled review and recommendation of an RFP and a new ground lease for 60-by-60-foot hangars.

Discussed
discussed

Commission discussed negotiation language in hangar RFP

On January 9, 2024, officials discussed negotiating with the highest-scoring proposal and clarifying the RFP exhibit that defines the lease area.

Discussed
discussed

Commission discussed RFP scoring and conflict safeguards

On November 9, 2023, the Airport Commission discussed lease terms, scoring proposals, and using a separate scoring group because some board members could submit proposals.

Discussed
discussed

Commission outlined four hangar lease areas

At an October 12, 2023 work session, officials discussed having Lead Edge and the county attorney prepare a preliminary package for four 60-by-60-foot ground-lease areas.

Discussed
discussed

Commission considered funding hangar-site preparation

On August 10, 2023, officials considered including hangar-site preparation in a possible FY2025 GDOT request with a 75%/25% split. The consultant said GDOT would not fund hangar construction.

Discussed
discussed

Commission discussed an RFP approach for hangars

At its June 5, 2023 work session, the Airport Commission discussed using an RFP for an interested party to build hangars to airport-developed plans.

Discussed
discussed

Commission began considering private hangar partnerships

In May 2023, the Airport Commission discussed a public-private approach for hangars, including design control and potential capacity. Officials noted 74 based aircraft and that two 10-unit T-hangars could raise that to 94.

Still unresolved

What is not yet known

These are evidence gaps, not assumptions. They remain open until a dependable source closes them.

  1. The July 2024 record confirms approval of two ground leases, but not lease execution, construction, completion or occupancy.
  2. The estimated $450,000 combined hangar value and potential revenues described in the July 2024 minutes are projections, not confirmed results.
  3. No record establishes whether proposed state support for site preparation was requested or awarded.
Newsroom notes1 open check on the record

How the newsroom is still working this matter. These are process notes, not reported facts.

Research the record

Search the underlying agendas, minutes, and documents.

Search supporting records