The cited official record ends with the November 27, 2023 entry and does not establish a later final outcome.
Habersham’s commercial-property assessment plan still lacks a documented contract
Assessors recommended McCormick Solutions for countywide commercial and industrial reviews, but public minutes do not confirm a commission vote or signed agreement.
At a glance
What this means now
The story
Habersham County’s plan to bring in McCormick Solutions for a countywide review of commercial and industrial property assessments remained unresolved in the public record after officials discussed a path to signing the agreement in July 2023. Staff told officials the county manager had been approved to sign after county-attorney review, but the chairperson asked to review the contract before it was signed, and the minutes do not record an executed agreement.
The proposed contract could affect how the county values a broad class of taxable property, not just a single appeal or parcel. McCormick was expected to value commercial and industrial properties, measure buildings and take photographs, while county field appraisers focused on residential reviews. Assessors presented that division of work as a response to a staffing shortage in the Tax Assessors Office.
The documented effort began June 26, 2023, when the Board of Assessors approved a recommendation that county commissioners hire McCormick Solutions. A month later, discussion shifted from the recommendation itself to the proposed contract’s review and signing. By November, the board was discussing a broader reevaluation process anticipated to begin in tax year 2025, with members saying commercial properties should be handled first and expecting information from WinGap in early December.
The Board of Assessors backed the McCormick recommendation as a way to direct scarce county appraisal capacity toward residential work while an outside firm handled commercial and industrial reviews. In the July discussion, staff described attorney review and asserted that the county manager had authority to sign. The chairperson, however, sought to see the contract first. In November, board members favored a commercial-first sequence for the contemplated reevaluation and discussed state recommendations involving WinGap.
Several actions are documented: assessors approved a recommendation, officials discussed contract review and signing, and the board continued reevaluation planning. What is not documented is equally important. The July minutes preserve staff’s statement about signing approval but contain no motion, vote tally or signed contract. They also do not establish that the Board of Commissioners acted on the recommendation, identify final contract terms, or show that McCormick performed the proposed work.
The next meaningful public step would be a county commission action or an executed agreement that identifies whether McCormick Solutions was formally retained and on what terms. Later assessment or reevaluation records could clarify whether the commercial-first plan discussed for tax year 2025 proceeded and whether WinGap information informed it. Until then, the record leaves unanswered whether the assessors’ recommendation became a completed procurement and how any planned work was carried out.
Arguments in the record
Positions presented publicly
Assessors recommended an outside commercial and industrial review while county field appraisers concentrated on residential properties amid a staffing shortage.
During the July contract discussion, the chairperson asked to see the agreement before it was signed.
What happened
How this issue got here
Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.
DiscussedconfirmedBoard discussed commercial-first reevaluation planning
On November 27, 2023, the Board discussed the RFP, the state recommendation for WinGap and a reevaluation planned to begin in tax year 2025. Members said they wanted commercial properties addressed first, with WinGap expected to provide information in early December.
+
Board discussed commercial-first reevaluation planning
On November 27, 2023, the Board discussed the RFP, the state recommendation for WinGap and a reevaluation planned to begin in tax year 2025. Members said they wanted commercial properties addressed first, with WinGap expected to provide information in early December.
DiscussedconfirmedOfficials discussed review before assessment-contract signing
On July 24, 2023, officials discussed commercial and industrial assessment work. The minutes record staff saying the county manager had been approved to sign the contract after county-attorney review, while the chairperson asked to see it before it was signed; the minutes do not document a signing or vote details for that stated authorization.
+
Officials discussed review before assessment-contract signing
On July 24, 2023, officials discussed commercial and industrial assessment work. The minutes record staff saying the county manager had been approved to sign the contract after county-attorney review, while the chairperson asked to see it before it was signed; the minutes do not document a signing or vote details for that stated authorization.
ApprovedconfirmedAssessors recommended McCormick assessment contract
On June 26, 2023, the Board of Assessors approved recommending a contract with McCormick Solutions to the Board of Commissioners. The proposed work would cover valuations, building measurements and photos for the county’s industrial and commercial properties while county field appraisers focused on residential reviews amid a staffing shortage.
+
Assessors recommended McCormick assessment contract
On June 26, 2023, the Board of Assessors approved recommending a contract with McCormick Solutions to the Board of Commissioners. The proposed work would cover valuations, building measurements and photos for the county’s industrial and commercial properties while county field appraisers focused on residential reviews amid a staffing shortage.
Still unresolved
What is not yet known
These are evidence gaps, not assumptions. They remain open until a dependable source closes them.
- The July minutes report staff’s statement that the county manager had approval to sign after attorney review, but do not include a motion, vote tally or executed contract.
- The record does not document Board of Commissioners action on the recommendation or confirm that the McCormick Solutions contract was signed.
Research the record