The runway closed from February 16 to March 6, 2026 for installation of new LED runway, threshold and taxiway lights, a new beacon and updated signage, with work having begun February 2. A final walkthrough in May 2026 turned up minor punch-list items, and by July the commission said the contractor had officially completed the punch list and removed leftover materials. As of the August 2026 meeting, about $117,000 remained unpaid pending the project's closeout.
Habersham County completes airport runway lighting project, final payment still pending
A GDOT-funded rebuild of the airport's runway and taxiway lighting is finished after a monthlong runway closure, but the county has not yet paid out roughly $117,000 held back from the contractor.
August 11, 2026: Airport lighting project retainage payment pending closeout
No next step has been documented.
At a glance
What this means now
The story
In early 2025 the Habersham County Airport Commission said a runway and taxiway lighting project was in design, with the Georgia Department of Transportation planning to fund the runway and taxiway lighting work together.
The project went out to bid in April 2025 and closed May 6. The Airport Commission voted 5-0 on May 13 to recommend awarding the bid to R.G. Tenney, the low bidder at $1,176,600, which the commission said was under its budgeted amount. The Habersham County Board of Commissioners voted 5-0 on May 19 to award the bid and authorize the county manager to sign related documents; a GDOT contract before the board capped state reimbursement at $882,450 or 75% of the $1,176,600 construction cost, whichever is less.
By September 2025 the construction contract with RG Tenney Electrical had been executed, with a 30-day contract time that included a 15-day runway closure. In October the Airport Commission said the contractor was still waiting on materials and would not start until all materials were on site; by November the commission said phase one was slated to begin January 5, 2026.
The runway closed from February 16 to March 6, 2026 for installation of new LED runway, threshold and taxiway lights, a new beacon and updated signage, with work having begun February 2. A final walkthrough in May 2026 turned up minor punch-list items, and by July the commission said the contractor had officially completed the punch list and removed leftover materials. As of the August 2026 meeting, about $117,000 remained unpaid pending the project's closeout.
What happened
How this issue got here
Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.
Appeared on agendaproposedAirport project update from Kimley-Horn consultant Rebecca Collins
Airport Update – Rebecca Collins, Kimley-Horn
+
Airport project update from Kimley-Horn consultant Rebecca Collins
Airport Update – Rebecca Collins, Kimley-Horn
DiscusseddiscussedAirport lighting project retainage payment pending closeout
Approximately $117,000
remains unpaid pending
ptoject closeout.
+
Airport lighting project retainage payment pending closeout
Approximately $117,000 remains unpaid pending ptoject closeout.
DiscusseddiscussedRunway overlay project completion by contractor
The contractor has officially completed the runway overlay punch list and have
removed the tocks that were left behind.
+
Runway overlay project completion by contractor
The contractor has officially completed the runway overlay punch list and have removed the tocks that were left behind.
Appeared on agendaproposedAirport project update presented by Rebecca Collins of Kimley-Horn
Airport Update – Rebecca Collins, Kimley-Horn
+
Airport project update presented by Rebecca Collins of Kimley-Horn
Airport Update – Rebecca Collins, Kimley-Horn
Appeared on agendaproposedAirport update presentation from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport update presentation from Lead Edge Design Group
Airport Update: Lead Edge Design Group
DiscusseddiscussedRunway/taxiway lighting project punch-list and final walkthrough with Lead Edge Design Group
a final walkthrough had been completed with Lead Edge regarding the
lighting project. Several minor punch-list items were identified
+
Runway/taxiway lighting project punch-list and final walkthrough with Lead Edge Design Group
a final walkthrough had been completed with Lead Edge regarding the lighting project. Several minor punch-list items were identified
Appeared on agendaproposedAirport project update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport project update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
DiscusseddiscussedRunway lighting project and related runway closure
The runway lighting project began on February 2.
+
Runway lighting project and related runway closure
The runway lighting project began on February 2.
DiscusseddiscussedAirfield lighting project and runway closure for LED lighting installation
The runway will be closed from February 16" through March 6" to allow for the installation of new LED runway,
threshold, and taxiway lights, a new beacon, and updated signage.
+
Airfield lighting project and runway closure for LED lighting installation
The runway will be closed from February 16" through March 6" to allow for the installation of new LED runway, threshold, and taxiway lights, a new beacon, and updated signage.
Appeared on agendaproposedAirport improvement project update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport improvement project update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
DiscusseddiscussedRunway and taxiway LED lighting project with Lead Edge Design Group
Phase one is slated to begin on Monday, January 5, 2026.
+
Runway and taxiway LED lighting project with Lead Edge Design Group
Phase one is slated to begin on Monday, January 5, 2026.
Appeared on agendaproposedAirport update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
DiscusseddiscussedAirport lighting project with Lead Edge Design Group
They are still
waiting on materials and will not begin the project until all materials are on site.
+
Airport lighting project with Lead Edge Design Group
They are still waiting on materials and will not begin the project until all materials are on site.
Appeared on agendaproposedAirport update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
DiscusseddiscussedRunway Lighting Project with GDOT and contractor RG Tenney Electrical
The contract between the county and the contractor RG Tenney Electrical has also been executed.
+
Runway Lighting Project with GDOT and contractor RG Tenney Electrical
The contract between the county and the contractor RG Tenney Electrical has also been executed.
Appeared on agendaproposedAirport Update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport Update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
DiscusseddiscussedRunway rehabilitation/lighting project with Lead Edge Design Group (grant contract, contractor submittals, planned runway closure)
It will be a 30-day contract time, of which 15 days the runway
will be closed
+
Runway rehabilitation/lighting project with Lead Edge Design Group (grant contract, contractor submittals, planned runway closure)
It will be a 30-day contract time, of which 15 days the runway will be closed
Appeared on agendaproposedAirport development update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
+
Airport development update from Lead Edge Design Group
Airport Update: Lead Edge Design Group
mentionedunknownAirport field lighting project
FY2025 Habersham County Airport started work on airport field lighting project
which is partially funded by grant funds which the county is responsible for a match amount.
+
Airport field lighting project
FY2025 Habersham County Airport started work on airport field lighting project which is partially funded by grant funds which the county is responsible for a match amount.
DiscusseddiscussedAirport runway/taxiway lighting project (grant-funded, Lead Edge Design Group)
It will be a 30-day contract time, of which 15 days the runway will be
closed.
+
Airport runway/taxiway lighting project (grant-funded, Lead Edge Design Group)
It will be a 30-day contract time, of which 15 days the runway will be closed.
Showing 1–20 of 35 recorded steps.
Find a step on another page
These links also preserve bookmarks to earlier timeline steps.
- June 10, 2025: Airport improvement project update from Lead Edge Design Group
- June 10, 2025: Presentation on airport basics by Lead Edge Design Group ("Airport 101")
- May 19, 2025: GDOT contract for Habersham County Airport airfield lighting rehabilitation (Limited Participation)
- May 19, 2025: Award of bid for Airport Lighting Project
- May 19, 2025: Award of Bid for Airport Lighting Project
- May 19, 2025: Airport Airfield Lighting Project - bid acceptance and construction contracts
- May 13, 2025: Bid tabulation for the Airfield Lighting Project
- May 13, 2025: Airfield Lighting Project bid award recommendation to R.G. Tenney
- April 15, 2025: Airport runway lighting project out for bid
- April 15, 2025: Airport update from Lead Edge Design Group
- March 11, 2025: Runway and taxiway lighting project bid package (GDOT-funded)
- March 11, 2025: Airport project update from Lead Edge Design Group
- February 11, 2025: Airport project update from Lead Edge Design Group
- January 14, 2025: Airport lighting project design phase, pending GDOT comments
- January 14, 2025: Airport Update from Lead Edge Design Group
Research the record