Habersham safety-plan contract leaves county positioned for road grants, but follow-through remains unclear

Commission records describe Kimley-Horn’s selection to prepare a federally supported safety action plan, a document intended to identify projects that could compete for future infrastructure funding.

By NEGA Brief Newsroom

At a glance

What this means now

Where it stands

The cited official record ends with the April 21, 2025 entry and does not establish a later final outcome.

The story

Habersham County’s Board of Commissioners considered its Safe Streets for All Grant Safety Action Plan during an April 21, 2025 work session, with Chief Financial Officer and Interim County Manager Tim Sims briefing commissioners on a process that county records say led to Kimley-Horn being selected to complete the plan. The county’s issue profile classifies the matter as approved, while the April agenda passage itself presents it as an item for consideration and does not document a vote or other final action.

SourcesMeeting4829_7 Minutes for 04.21.25 BOC Work Session.pdfMinutes for 04.21.25 BOC Work Session

The plan matters because it is meant to turn traffic-safety concerns into a roadmap for future capital projects. County officials said the federal grant would help pay for a traffic engineer to prepare a safety action plan, which in turn could support applications for infrastructure grants to carry out solutions identified by the study. The plan does not itself commit the county to pursue those later grants or build any particular improvement.

SourcesMeeting4829_7 Minutes for 04.21.25 BOC Work Session.pdfMinutes for 04.21.25 BOC Work Session

According to the April 2025 county account, Habersham first applied for the Safe Streets for All grant in September 2022. The county said the grant was funded through the federal Build Back Better grant program. After that application, officials said an RFP was released in September 2023 and Kimley-Horn was selected to complete the safety action plan. The 2025 work-session discussion brought that earlier procurement and the plan’s prospective use before commissioners again.

SourcesMeeting4829_7 Minutes for 04.21.25 BOC Work Session.pdfMinutes for 04.21.25 BOC Work Session

County staff framed the plan as a practical tool rather than a promise of construction. Sims told commissioners that its value lay in helping Habersham seek future infrastructure funding for safety solutions identified during the study. That position preserves discretion for the Board of Commissioners: officials said the county has no obligation to apply for future grants, even though they described having the plan as beneficial. No separate position from residents, property owners, Kimley-Horn or commissioners is documented in the material here.

SourcesMeeting4829_7 Minutes for 04.21.25 BOC Work Session.pdfMinutes for 04.21.25 BOC Work Session

The county profile treats the safety-plan matter as approved as of April 21, 2025. Separately, the underlying work-session agenda language describes the item and the prior selection of Kimley-Horn, but expressly does not establish an outcome on its own. The record therefore supports that the county pursued the planning effort and identifies its intended grant-ready purpose; it does not establish which safety projects were selected, whether any later grant applications were filed, or whether construction resulted.

SourcesMeeting4829_7 Minutes for 04.21.25 BOC Work Session.pdfMinutes for 04.21.25 BOC Work Session

The next concrete public milestone would be a later county record showing implementation of the safety action plan, including any amendments, payments, project recommendations or applications for additional infrastructure grants. Until then, the central unanswered questions are what the plan recommended, how much the county ultimately spent, whether it sought follow-up funding, and whether any identified safety solution moved from planning into construction.

SourcesMeeting4829_7 Minutes for 04.21.25 BOC Work Session.pdfMinutes for 04.21.25 BOC Work Session

Arguments in the record

Positions presented publicly

County staff

County staff said the plan would help Habersham pursue future infrastructure grants for safety solutions identified in the study, while emphasizing that the county was not required to seek those grants.

Commission record

The county profile labels the matter approved, but the cited work-session agenda passage alone does not document the final action.

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Discussed
confirmed

Commission received Safe Streets safety-plan update

On April 21, 2025, the commission heard an update on the Safe Streets for All safety action plan. Staff said the federally funded grant supports traffic-engineering work to identify problem areas and prioritize road projects, helping position the county for future infrastructure-grant applications; the county may use participating IT and Road Department staff salaries as its in-kind match. The update described an RFP released in September 2023 and Kimley-Horn’s selection to complete the plan, but did not state a new commission vote or subsequent implementation action.

Still unresolved

What is not yet known

These are evidence gaps, not assumptions. They remain open until a dependable source closes them.

  1. The April 2025 work-session material reports prior grant and contractor status but does not document a new commission vote or later implementation outcome.