Habersham Development Authority keeps building out and selling lots in Phase II of Airport Business Park

The authority is overseeing new construction and courting developers for the remaining Phase II lots, even as it chases unpaid tenant bills in the park.

By NEGA Brief NewsroomLast checked October 1, 2026
Latest

June 11, 2026: Airport Business Park new signage for tenants

What happens next

No next step has been documented.

At a glance

What this means now

Where it stands

As of June 2026, the authority reported three active prospects for Airport Business Park and Phase II, including a developer who had expressed interest in moving quickly on a project, and tenants had asked for new signage to display their information.

The story

In January 2025 the Development Authority, which reported that activity on existing business park buildings such as the Higgins building was slow, voted 6-0 to amend a sale contract for its 0 Pyratich Drive property, then days later voted 6-0 to counteroffer on the sale at 5.007 acres for $45,000 per acre plus a 5% commission fee.

SourcesMeeting4814_Approved Minutes - January 9- 2025 Regular Meeting.pdfMeeting4880_Approved Minutes - January 22- 2025 Special Called Meeting.pdf

By February 2025 the authority had two prospects for Phase II, one nearing a closing, though a prospect called Project Hill withdrew from its contract. The Pyratich sale closed in March, with the authority receiving proceeds of $214,049.25, while a separate dispute arose over Wilson-Hutchinson's buyback of lots 5 and 7. By April, construction materials had been ordered for a Clearview building on the Pyratich site, and Wilson-Hutchinson had submitted plans for a 15,000-square-foot building on pad 7, across from the Higgins building.

SourcesMeeting4816_Approved Minutes - February 13- 2025 Regular Meeting.pdfMeeting4815_Approved Minutes - March 13- 2025 Regular Meeting.pdfMeeting4817_Approved Minutes - April 17- 2025 Regular Meeting.pdf

In June 2025 the authority voted 7-0 to approve updated Phase II business park covenants adding an association/dues requirement and a $500-per-month penalty for construction delays, and reviewed new layout renderings for the Phase II area.

SourcesMeeting4819_20250818112922254.pdf

Through the rest of 2025 the authority kept marketing the 15 acres still unsold in Phase II while dealing with nonpayment by tenant GTS Customs. Construction progressed into 2026: Clear View Enterprises was finishing a new building by January, and by June a 10,000-square-foot building on pad 6(B) was moving forward with an estoppel letter to help secure financing, while pad 7's permitting was delayed by issues with the City of Baldwin's new permitting company.

SourcesMeeting4824_20260109095530945.pdfMeeting4821_Approved Minutes - August 14- 2025 Regular Meeting.pdfMeeting5247_Minutes Draft - January 8- 2026 Regular Meeting.pdfMeeting5252_20260717101949886.pdf

As of June 2026, the authority reported three active prospects for Airport Business Park and Phase II, including a developer who had expressed interest in moving quickly on a project, and tenants had asked for new signage to display their information.

SourcesMeeting5252_20260717101949886.pdf

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Discussed
discussed

Phase I/II Airport Business Park lot discussion with SteelCell

Rope Roberts and Bryan Ferguson ate trying to arrange a meeting with SteelCell regarding an available lot in Phase H

Appeared on agenda
proposed

Phase II Business Park update

Phase II Business Park Update

Discussed
discussed

GTS Customs unpaid business park common services bills / possible letter to owner

G'S Customs has not paid any of the bills associated with the business park common setvices and owe a balance of $915.73

Appeared on agenda
proposed

Airport Business Park update, including GTS Customs letter

Airport Business Park Update o GTS Customs letter

Appeared on agenda
proposed

Phase II Business Park update

Phase II Business Park Update

Appeared on agenda
proposed

Airport Business Park update

Airport Business Park Update

Discussed
discussed

Administrative update on tenant accounts, including GTS Customs nonpayment

GTS Customs has not paid any of their invoices.

Appeared on agenda
proposed

Airport Business Park Update

1. Airport Business Park Update

Appeared on agenda
proposed

Phase II Business Park Update

2. Phase II Business Park Update

Discussed
discussed

Development Authority administrative update on past-due tenant accounts (TDB Southern Enterprises, Windstream, Wade Rhodes, GI'S Customs)

Patti sent out past due notices last month and has received payment from TDB Southern Enterprises.

Approved
confirmed

Updated business park covenants for Phase II (association/dues requirement, $500/month construction-delay penalty)

voted 7-0 to approve the updated business park covenants for Phase II.

Appeared on agenda
proposed

Airport Business Park development update

Airport Business Park Update

Appeared on agenda
proposed

Phase II Business Park development update

Phase II Business Park Update

Discussed
discussed

Phase II Business Park layout renderings

Bryan Ferguson brought two renderings for a proposed layout for Phase II.

Appeared on agenda
proposed

Updated business park covenants for Phase II

Consider/Discuss updated business park covenants for Phase II

Discussed
discussed

Business park billing worksheet / tenant balance due

the business park billing worksheet dated 3/12/25 which shows a balance due from tenants of $2,817.04.

Discussed
discussed

Phase II Business Park update: Clearview building construction on Pyratich site

construction materials have been ordered for the Clearview building on the Pyratich site, and they will be breaking ground soon.

Appeared on agenda
proposed

Airport Business Park Update

Airport Business Park Update

Discussed
discussed

Airport Business Park update: Wilson-Hutchinson development on lots 5 and 7

Wilson-Hutchinson have submitted plans and permits to build a 15,000 square foot building on pad 7, which is across from the Higgins building.

Appeared on agenda
proposed

Updated business park covenants for Phase II

Consider/Discuss updated business park covenants for Phase II

Showing 21–40 of 54 recorded steps.