NEGAbriefLocal records made useful
IssueFranklin Countyunder consideration

Iron foundry asks Georgia EPD to cap production at 30,000 tons a year

The facility has requested a production limit of 30,000 tons per year of iron poured, according to a Georgia EPD Air Protection Branch document. The company says the limit would keep its potential emissions below the threshold that triggers PSD major-source permitting, making it a PSD minor source instead.

Last checked September 30, 2026
Record

September 29, 2026 · Appeared on agenda

What happens next

No next step has been documented.

Source

TV-840156 nar ↗

This matter rests on a single official record so far. It stays compact until a later record adds to it.

Browse current issues →