The story
Georgia's Environmental Protection Division has drafted a permit condition capping CO2e emissions from each combined-cycle combustion turbine stack at the Thomas A. Smith Energy Facility at 1,270,090 tons during any twelve consecutive months.
The cap is part of a proposed renewal of the facility's Title V Operating Permit, which covers the electric power utility in Dalton. EPD has set a deadline of October 30, 2026 for the public to request a hearing during the comment period.