Cornelia water authority awards Hazel Creek pump station contract for $1,024,050

The project, funded partly by a state loan, will upgrade the raw water pump station that supplies the city's water system.

By NEGA Brief Newsroom
Latest

January 27, 2026: Hazel Creek Raw Water Pump Station Improvement

At a glance

What this means now

Where it stands

By January 2026, the authority's agenda and minutes showed the contract amount at $1,103,049.79, up from the original $1,024,050 award, with the agenda also referencing a 4.3 MGD figure for the project.

The story

The Cornelia Water & Sewerage Authority approved awarding the contract for the Hazel Creek Raw Water Pump Station Improvements to J. Brennon Construction for $1,024,050, to be funded in part by a $1,329,200 GEFA loan.

Sources4th Quarter Mintues 2024 Meeting 108.8 KBCornelia Water & Sewerage Authority Meeting Agenda for April 22 194.8 KB

In July 2025 the authority's minutes again recorded the award to J. Brennon Construction at $1,024,050, noting the figure would be updated with additions or deductions when available.

Sources2nd Quarter Mintues 2025 Meeting 109.5 KB

By January 2026, the authority's agenda and minutes showed the contract amount at $1,103,049.79, up from the original $1,024,050 award, with the agenda also referencing a 4.3 MGD figure for the project.

Sources2) Cornelia Water Authority Agenda for April 28, 2026 180.1 KBCornelia Water & Sewer Authority 4th Quarter Mintues 2025 153.2 KB

What happened

How this issue got here

Open any step for its supporting record. A proposal remains labeled as proposed until later evidence establishes an outcome.

Discussed
discussed

Hazel Creek Raw Water Pump Station Improvement

Awarded to J. Brennon Construction for $1,103,049.79

Discussed
discussed

Hazel Creek Raw Water Pump Station Improvement

Awarded to J. Brennon Construction for $1,103,049.79

Approved
confirmed

Hazel Creek raw water pump station improvements

Awarded to J. Brennon Construction for $1,024,050- update with additions/deductions when available

Approved
confirmed

Hazel Creek Raw Water Pump Station Improvements

GEFA Loan - $1,329,200. Awarded to J. Brennon Construction for $1,024,050

Discussed
discussed

Hazel Creek Raw Water Pump Station Improvements

GEFA Loan - $1,329,200. Awarded to J. Brennon Construction for $1,024,050